Bldg. E18 - 4/13 - Critical Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Apr 11 10:28:56 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451104BFE@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'AUFIERO@MIT.EDU'" <AUFIERO@MIT.EDU>,
        "'nedivi@mit.edu'"
	 <nedivi@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'jmganno@mit.edu'" <jmganno@MIT.EDU>,
        "'rmelo@mit.edu'" <rmelo@MIT.EDU>, "'wardd@mit.edu'" <wardd@MIT.EDU>,
        "'amba@mit.edu'" <amba@MIT.EDU>, "'shyoung@mit.edu'" <shyoung@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 11 Apr 2000 10:28:11 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	AUFIERO@MIT.EDU; nedivi@mit.edu; shutdowns@mit.edu; jmganno@mit.edu;
> rmelo@mit.edu; wardd@mit.edu; amba@mit.edu; shyoung@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E18 - 4/13 - Critical Shutdown Request
> 
> 
The following Critical shutdown request for Bldg. E18 on Thursday, 4/13 is
for your information.  Would you please let me know whether this does or
does not have your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Critical
> Building: E18
> Date: 4/13/00
> Day: Thursday
> Time: 7 AM - 8:30 AM
> System: RO/DI Water
> Duration: 1 1/2 hours
> Reason: 
> Install H & A switch. Water should be available by gravity.
> 
> Effect: 
> Minimal loss of RO/De-ionized water during shutdown period.  Should not
> take more than  10 to 15 minutes without complications.
> 
> 