Fwd: N42 Construction schedule...

daemon@ATHENA.MIT.EDU (Sally J. Persing)
Wed Mar 29 11:38:53 2000

Mime-Version: 1.0
Content-Type: multipart/alternative; boundary="============_-1257774568==_ma============"
Message-Id: <v04020a01b507ddda0a08@[18.152.0.173]>
Date: Wed, 29 Mar 2000 11:24:48 -0500
To: bmurphy@MIT.EDU, joewelch@MIT.EDU, hotline@MIT.EDU
From: "Sally J. Persing" <sjpers@MIT.EDU>

--============_-1257774568==_ma============
Content-Type: text/plain; charset="us-ascii"

Hi, Athena Team--
	I thought you should see this and specifically pay attention to the
large, red paragraph. Let me know if there's anything I can do. Thanks.
				~~~~~Sj

>Date: Tue, 28 Mar 2000 21:01:09 -0500
>To: isn42@mit.edu
>From: "Christine M. Cavanna" <cavanna@MIT.EDU>
>Subject: N42 Construction schedule...
>Cc: itlt@mit.edu, wjfitz@mit.edu
>
>Hi everyone,
>Here is the latest and greatest on the N42 lower level construction
>project.  I met this morning with the project manager, the architect and
>the contractors to review the work schedule and do a walk thru of the area.
>We are on target to begin the work next week, however due to some noisy
>disruption segments of the work they will not begin on Monday, 4/3 but will
>begin on Wed, 4/5.
>
>Below is the schedule as it stands today:
>	Wed. 4/5 - Construction begins
>		Roll back of carpet - to be salvaged
>
>		5 p.m. - cut two exploratory holes in slab to look for
>		conduit and sanitary lines.
>		THIS EFFORT MAY BE NOISY AND THUS IS SCHEDULED FOR AFTER
>		HOURS.
>
>	Thur and Fri, 4/6 & 7 - Build dust barriers
>
>		IMPORTANT:  On Saturday, 4/8 the contractors will be sawcutting
>			the slab.  Because there is conduit in the ground
>			below the slab and there is a slight chance that it
>			could be hit, I am suggesting that any computer
>			equipment containing critical data that could be lost
>			if power is interrupted be powered down by END OF
>			BUSINESS ON FRIDAY, 4/7.
>
>	Sat, 4/8 - Sawcutting and Demolition of Slab -- this effort is very
>		noisy and disruptive thus scheduled for the weekend.
>
>	Mon, 4/10 - 5 p.m. Vacumn truck to suck out dirt from pit dug over
>		the weekend.  This again is very noisy and disruptive.
>
>Those are the major dates of importance as we begin this project.  I will
>be meeting with the project team on a weekly basis throughout the project
>and will send periodic updates as new developments arise.
>
>The project is slated to take approximately 6 weeks bringing us into
>early/mid-May.  There is one long lead time item that will be installed in
>June but shouldn't impact our ability to inhabit the area.
>
>For security reasons, either myself or another IS staff member will be
>present to oversee the work during after hours and on Saturday, 4/8.
>
>I would appreciate that we minimize the traffic flow in and out of the
>building through the back courtyard entrance during the construction
>period.  However, we can still utilize the bathrooms, showers and the bike
>room during construction.
>
>If you have any questions or concerns, please let me know.  Otherwise, stay
>tuned as the project develops for more updates.
>
>Thanks again for your patience!
>Christine
>
				~~~~~ Sj
--============_-1257774568==_ma============
Content-Type: text/enriched; charset="us-ascii"

Hi, Athena Team--

	I thought you should see this and specifically pay attention to the
large, red paragraph. Let me know if there's anything I can do.
Thanks.

				~~~~~Sj


>Date: Tue, 28 Mar 2000 21:01:09 -0500

>To: isn42@mit.edu

>From: "Christine M. Cavanna" <<cavanna@MIT.EDU>

>Subject: N42 Construction schedule...

>Cc: itlt@mit.edu, wjfitz@mit.edu

>

>Hi everyone,

>Here is the latest and greatest on the N42 lower level construction

>project.  I met this morning with the project manager, the architect
and

>the contractors to review the work schedule and do a walk thru of the
area.

>We are on target to begin the work next week, however due to some
noisy

>disruption segments of the work they will not begin on Monday, 4/3 but
will

>begin on Wed, 4/5.

>

>Below is the schedule as it stands today:

>	Wed. 4/5 - Construction begins

>		Roll back of carpet - to be salvaged

>

>		5 p.m. - cut two exploratory holes in slab to look for

>		conduit and sanitary lines.

>		THIS EFFORT MAY BE NOISY AND THUS IS SCHEDULED FOR AFTER

>		HOURS.

>

>	Thur and Fri, 4/6 & 7 - Build dust barriers

>

>		<color><param>FFFF,0000,0000</param><bigger><bigger>IMPORTANT:  On
Saturday, 4/8 the contractors will be sawcutting

>			the slab.  Because there is conduit in the ground

>			below the slab and there is a slight chance that it

>			could be hit, I am suggesting that any computer

>			equipment containing critical data that could be lost

>			if power is interrupted be powered down by END OF

>			BUSINESS ON FRIDAY, 4/7.

</bigger></bigger></color>>

>	Sat, 4/8 - Sawcutting and Demolition of Slab -- this effort is very

>		noisy and disruptive thus scheduled for the weekend.

>

>	Mon, 4/10 - 5 p.m. Vacumn truck to suck out dirt from pit dug over

>		the weekend.  This again is very noisy and disruptive.

>

>Those are the major dates of importance as we begin this project.  I
will

>be meeting with the project team on a weekly basis throughout the
project

>and will send periodic updates as new developments arise.

>

>The project is slated to take approximately 6 weeks bringing us into

>early/mid-May.  There is one long lead time item that will be
installed in

>June but shouldn't impact our ability to inhabit the area.

>

>For security reasons, either myself or another IS staff member will
be

>present to oversee the work during after hours and on Saturday, 4/8.

>

>I would appreciate that we minimize the traffic flow in and out of
the

>building through the back courtyard entrance during the construction

>period.  However, we can still utilize the bathrooms, showers and the
bike

>room during construction.

>

>If you have any questions or concerns, please let me know.  Otherwise,
stay

>tuned as the project develops for more updates.

>

>Thanks again for your patience!

>Christine

>