[50453] in Hotline Meeting
Fwd: N42 Construction schedule...
daemon@ATHENA.MIT.EDU (Sally J. Persing)
Wed Mar 29 11:38:53 2000
Mime-Version: 1.0
Content-Type: multipart/alternative; boundary="============_-1257774568==_ma============"
Message-Id: <v04020a01b507ddda0a08@[18.152.0.173]>
Date: Wed, 29 Mar 2000 11:24:48 -0500
To: bmurphy@MIT.EDU, joewelch@MIT.EDU, hotline@MIT.EDU
From: "Sally J. Persing" <sjpers@MIT.EDU>
--============_-1257774568==_ma============
Content-Type: text/plain; charset="us-ascii"
Hi, Athena Team--
I thought you should see this and specifically pay attention to the
large, red paragraph. Let me know if there's anything I can do. Thanks.
~~~~~Sj
>Date: Tue, 28 Mar 2000 21:01:09 -0500
>To: isn42@mit.edu
>From: "Christine M. Cavanna" <cavanna@MIT.EDU>
>Subject: N42 Construction schedule...
>Cc: itlt@mit.edu, wjfitz@mit.edu
>
>Hi everyone,
>Here is the latest and greatest on the N42 lower level construction
>project. I met this morning with the project manager, the architect and
>the contractors to review the work schedule and do a walk thru of the area.
>We are on target to begin the work next week, however due to some noisy
>disruption segments of the work they will not begin on Monday, 4/3 but will
>begin on Wed, 4/5.
>
>Below is the schedule as it stands today:
> Wed. 4/5 - Construction begins
> Roll back of carpet - to be salvaged
>
> 5 p.m. - cut two exploratory holes in slab to look for
> conduit and sanitary lines.
> THIS EFFORT MAY BE NOISY AND THUS IS SCHEDULED FOR AFTER
> HOURS.
>
> Thur and Fri, 4/6 & 7 - Build dust barriers
>
> IMPORTANT: On Saturday, 4/8 the contractors will be sawcutting
> the slab. Because there is conduit in the ground
> below the slab and there is a slight chance that it
> could be hit, I am suggesting that any computer
> equipment containing critical data that could be lost
> if power is interrupted be powered down by END OF
> BUSINESS ON FRIDAY, 4/7.
>
> Sat, 4/8 - Sawcutting and Demolition of Slab -- this effort is very
> noisy and disruptive thus scheduled for the weekend.
>
> Mon, 4/10 - 5 p.m. Vacumn truck to suck out dirt from pit dug over
> the weekend. This again is very noisy and disruptive.
>
>Those are the major dates of importance as we begin this project. I will
>be meeting with the project team on a weekly basis throughout the project
>and will send periodic updates as new developments arise.
>
>The project is slated to take approximately 6 weeks bringing us into
>early/mid-May. There is one long lead time item that will be installed in
>June but shouldn't impact our ability to inhabit the area.
>
>For security reasons, either myself or another IS staff member will be
>present to oversee the work during after hours and on Saturday, 4/8.
>
>I would appreciate that we minimize the traffic flow in and out of the
>building through the back courtyard entrance during the construction
>period. However, we can still utilize the bathrooms, showers and the bike
>room during construction.
>
>If you have any questions or concerns, please let me know. Otherwise, stay
>tuned as the project develops for more updates.
>
>Thanks again for your patience!
>Christine
>
~~~~~ Sj
--============_-1257774568==_ma============
Content-Type: text/enriched; charset="us-ascii"
Hi, Athena Team--
I thought you should see this and specifically pay attention to the
large, red paragraph. Let me know if there's anything I can do.
Thanks.
~~~~~Sj
>Date: Tue, 28 Mar 2000 21:01:09 -0500
>To: isn42@mit.edu
>From: "Christine M. Cavanna" <<cavanna@MIT.EDU>
>Subject: N42 Construction schedule...
>Cc: itlt@mit.edu, wjfitz@mit.edu
>
>Hi everyone,
>Here is the latest and greatest on the N42 lower level construction
>project. I met this morning with the project manager, the architect
and
>the contractors to review the work schedule and do a walk thru of the
area.
>We are on target to begin the work next week, however due to some
noisy
>disruption segments of the work they will not begin on Monday, 4/3 but
will
>begin on Wed, 4/5.
>
>Below is the schedule as it stands today:
> Wed. 4/5 - Construction begins
> Roll back of carpet - to be salvaged
>
> 5 p.m. - cut two exploratory holes in slab to look for
> conduit and sanitary lines.
> THIS EFFORT MAY BE NOISY AND THUS IS SCHEDULED FOR AFTER
> HOURS.
>
> Thur and Fri, 4/6 & 7 - Build dust barriers
>
> <color><param>FFFF,0000,0000</param><bigger><bigger>IMPORTANT: On
Saturday, 4/8 the contractors will be sawcutting
> the slab. Because there is conduit in the ground
> below the slab and there is a slight chance that it
> could be hit, I am suggesting that any computer
> equipment containing critical data that could be lost
> if power is interrupted be powered down by END OF
> BUSINESS ON FRIDAY, 4/7.
</bigger></bigger></color>>
> Sat, 4/8 - Sawcutting and Demolition of Slab -- this effort is very
> noisy and disruptive thus scheduled for the weekend.
>
> Mon, 4/10 - 5 p.m. Vacumn truck to suck out dirt from pit dug over
> the weekend. This again is very noisy and disruptive.
>
>Those are the major dates of importance as we begin this project. I
will
>be meeting with the project team on a weekly basis throughout the
project
>and will send periodic updates as new developments arise.
>
>The project is slated to take approximately 6 weeks bringing us into
>early/mid-May. There is one long lead time item that will be
installed in
>June but shouldn't impact our ability to inhabit the area.
>
>For security reasons, either myself or another IS staff member will
be
>present to oversee the work during after hours and on Saturday, 4/8.
>
>I would appreciate that we minimize the traffic flow in and out of
the
>building through the back courtyard entrance during the construction
>period. However, we can still utilize the bathrooms, showers and the
bike
>room during construction.
>
>If you have any questions or concerns, please let me know. Otherwise,
stay
>tuned as the project develops for more updates.
>
>Thanks again for your patience!
>Christine
>