[50427] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldgs. E23 and E25 - 4/1-2 Update

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Mar 27 13:46:29 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451104B50@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'avel@med.mit.edu'" <avel@med.mit.edu>,
        "'bengel@mit.edu'"
	 <bengel@MIT.EDU>,
        "'edwa@med.mit.edu'" <edwa@med.mit.edu>,
        "'roge@med.mit.edu'" <roge@med.mit.edu>,
        "'bmalone@mit.edu'"
	 <bmalone@MIT.EDU>,
        "'cpoon@mit.edu'" <cpoon@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'elworthi@mit.edu'"
	 <elworthi@MIT.EDU>,
        "'jmganno@mit.edu'" <jmganno@MIT.EDU>,
        "'lippertm@mit.edu'" <lippertm@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'shyoung@mit.edu'" <shyoung@MIT.EDU>,
        "'jrauch@mit.edu'" <jrauch@MIT.EDU>,
        "'hegarty@mit.edu'"
	 <hegarty@MIT.EDU>,
        "'andrea@psyche.mit.edu'" <andrea@psyche.mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>
Date: Mon, 27 Mar 2000 13:45:59 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	'avel@med.mit.edu'; 'bengel@mit.edu'; 'edwa@med.mit.edu';
> 'roge@med.mit.edu'; 'bmalone@mit.edu'; 'cpoon@mit.edu';
> 'shutdowns@mit.edu'; 'elworthi@mit.edu'; 'jmganno@mit.edu';
> 'lippertm@mit.edu'; 'schedule@mit.edu'; 'shyoung@mit.edu';
> 'jrauch@mit.edu'; 'hegarty@mit.edu'; 'andrea@psyche.mit.edu'
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: 	Bldgs. E23 and E25 - 4/1-2 Update
> 
> 
The following revised shutdown for Bldgs. E23 and E25 on Saturday, 4/1 is
again for your review and comment.  Would you please let me know if this new
shtudown request better suits your schedules.

Thank you again for your time.

Andrea Nichols
Operations Center
8-7872


> Status: Normal
> Building: E23 and E25 - Entire Buildings
> Date: 4/1/02
> Day: Saturday
> Time: 12 midnight (4/1) - 4 AM (4/2)
> System: Hot and cold domestic, hot and cold lab processed water
> Duration: 4 hours
> Reason: 
> To make repairs to booster pumps.
> 
> Effect: 
> Loss of hot and cold domestic water (water for toilets, showers, bathroom,
> kitchen faucets, safety showers, eye washes, drinking fountains); hot and
> cold lab process water (water for lab equipment, bunsen burners) during
> the 4-hour shutdown period.
> 
> 