[50427] in Hotline Meeting
Bldgs. E23 and E25 - 4/1-2 Update
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Mar 27 13:46:29 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104B50@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'avel@med.mit.edu'" <avel@med.mit.edu>,
"'bengel@mit.edu'"
<bengel@MIT.EDU>,
"'edwa@med.mit.edu'" <edwa@med.mit.edu>,
"'roge@med.mit.edu'" <roge@med.mit.edu>,
"'bmalone@mit.edu'"
<bmalone@MIT.EDU>,
"'cpoon@mit.edu'" <cpoon@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'elworthi@mit.edu'"
<elworthi@MIT.EDU>,
"'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'lippertm@mit.edu'" <lippertm@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'shyoung@mit.edu'" <shyoung@MIT.EDU>,
"'jrauch@mit.edu'" <jrauch@MIT.EDU>,
"'hegarty@mit.edu'"
<hegarty@MIT.EDU>,
"'andrea@psyche.mit.edu'" <andrea@psyche.mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>
Date: Mon, 27 Mar 2000 13:45:59 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: 'avel@med.mit.edu'; 'bengel@mit.edu'; 'edwa@med.mit.edu';
> 'roge@med.mit.edu'; 'bmalone@mit.edu'; 'cpoon@mit.edu';
> 'shutdowns@mit.edu'; 'elworthi@mit.edu'; 'jmganno@mit.edu';
> 'lippertm@mit.edu'; 'schedule@mit.edu'; 'shyoung@mit.edu';
> 'jrauch@mit.edu'; 'hegarty@mit.edu'; 'andrea@psyche.mit.edu'
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldgs. E23 and E25 - 4/1-2 Update
>
>
The following revised shutdown for Bldgs. E23 and E25 on Saturday, 4/1 is
again for your review and comment. Would you please let me know if this new
shtudown request better suits your schedules.
Thank you again for your time.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E23 and E25 - Entire Buildings
> Date: 4/1/02
> Day: Saturday
> Time: 12 midnight (4/1) - 4 AM (4/2)
> System: Hot and cold domestic, hot and cold lab processed water
> Duration: 4 hours
> Reason:
> To make repairs to booster pumps.
>
> Effect:
> Loss of hot and cold domestic water (water for toilets, showers, bathroom,
> kitchen faucets, safety showers, eye washes, drinking fountains); hot and
> cold lab process water (water for lab equipment, bunsen burners) during
> the 4-hour shutdown period.
>
>