[50410] in Hotline Meeting
E23 and E25 4/1 and 4/2 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Mar 24 08:20:41 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104B33@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'avel@med.mit.edu'" <avel@med.mit.edu>,
"'bengel@mit.edu'"
<bengel@MIT.EDU>,
"'edwa@med.mit.edu'" <edwa@med.mit.edu>,
"'roge@med.mit.edu'" <roge@med.mit.edu>,
"'bmalone@mit.edu'"
<bmalone@MIT.EDU>,
"'cpoon@mit.edu'" <cpoon@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'elworthi@mit.edu'"
<elworthi@MIT.EDU>,
"'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'lippertm@mit.edu'" <lippertm@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'shyoung@mit.edu'" <shyoung@MIT.EDU>,
"'jrauch@mit.edu'" <jrauch@MIT.EDU>,
"'hegarty@mit.edu'"
<hegarty@MIT.EDU>,
"'andrea@psyche.mit.edu'" <andrea@psyche.mit.edu>,
"'bnbauer@mit.edu'" <bnbauer@MIT.EDU>,
"'lfeltner@mit.edu'"
<lfeltner@MIT.EDU>,
"'cjbeal@mit.edu'" <cjbeal@MIT.EDU>, "'cac@mit.edu'"
<cac@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 24 Mar 2000 08:20:21 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: 'avel@med.mit.edu'; 'bengel@mit.edu'; 'edwa@med.mit.edu';
> 'roge@med.mit.edu'; 'bmalone@mit.edu'; 'cpoon@mit.edu';
> 'shutdowns@mit.edu'; 'elworthi@mit.edu'; 'jmganno@mit.edu';
> 'lippertm@mit.edu'; 'schedule@mit.edu'; 'shyoung@mit.edu';
> 'jrauch@mit.edu'; 'hegarty@mit.edu'; 'andrea@psyche.mit.edu';
> 'bnbauer@mit.edu'; 'lfeltner@mit.edu'; 'cjbeal@mit.edu'; 'cac@mit.edu'
> Cc: shutdown@plant.mit.edu
> Subject: E23 and E25 4/1 and 4/2 - Shutdown Request
>
>
The following revised shutdown for Bldgs. E23 and E25 on Saturday, 4/1 is
again for your review and comment. Would you please let me know if this new
shtudown request better suits your schedules.
Thank you again for your time.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E23 and E25
> Date: 4/1/00
> Day: Saturday
> Time: 8 PM - 12 midnight
> System: Hot and cold domestic, hot and cold lab processed water
> Duration: 4 hours
> Reason:
> To repair booster pumps.
>
> Effect:
> Loss of hot and cold domestic water (water for toilets, showers, bathroom,
> kitchen faucets, safety showers, eye washes, drinking fountains); hot and
> cold lab process water (water for lab equipment, bunsen burners) during
> the 12-hour shutdown period..
>
>