E23 and E25 4/1 and 4/2 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Mar 21 13:44:14 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104B06@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'avel@med.mit.edu'" <avel@med.mit.edu>,
"'bengel@mit.edu'"
<bengel@MIT.EDU>,
"'sdowney@mit.edu'" <sdowney@MIT.EDU>,
"'edwa@med.mit.edu'" <edwa@med.mit.edu>,
"'roge@med.mit.edu'"
<roge@med.mit.edu>,
"'bmalone@mit.edu'" <bmalone@MIT.EDU>,
"'cpoon@mit.edu'" <cpoon@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'elworthi@mit.edu'" <elworthi@MIT.EDU>,
"'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'lippertm@mit.edu'"
<lippertm@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shyoung@mit.edu'" <shyoung@MIT.EDU>,
"'jrauch@mit.edu'"
<jrauch@MIT.EDU>,
"'hegarty@mit.edu'" <hegarty@MIT.EDU>,
"'andrea@psyche.mit.edu'" <andrea@psyche.mit.edu>,
"'bnbauer@mit.edu'"
<bnbauer@MIT.EDU>,
"'lfeltner@mit.edu'" <lfeltner@MIT.EDU>,
"'cjbeal@mit.edu'" <cjbeal@MIT.EDU>, "'cac@mit.edu'" <cac@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 21 Mar 2000 13:43:57 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: avel@med.mit.edu; bengel@mit.edu; sdowney@mit.edu; edwa@med.mit.edu;
> roge@med.mit.edu; bmalone@mit.edu; cpoon@mit.edu; shutdowns@mit.edu;
> elworthi@mit.edu; jmganno@mit.edu; lippertm@mit.edu; schedule@mit.edu;
> shyoung@mit.edu; jrauch@mit.edu; hegarty@mit.edu; andrea@psyche.mit.edu;
> bnbauer@mit.edu; lfeltner@mit.edu; cjbeal@mit.edu; cac@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: E23 and E25 4/1 and 4/2 - Shutdown Request
>
>
The following shutdown request for Bldgs. E23 and E25 on Saturday, 4/1 and
Sunday, 4/2 is for your information and comment. Would you please let me
know whether this does or does not meet with your approval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E23 and E25
> Date: 4/1/02
> Day: Saturday
> Time: 6 PM (4/1) - 6 AM (4/2)
> System: Hot and cold domestic, hot and cold lab process water
> Duration: 12 hours
> Reason:
> To make repairs to booster pumps.
>
> Effect:
> Loss of hot and cold domestic water (water for toilets, bathroom, kitchen
> faucets, safety showers, eye washes, drinking fountains); hot and cold lab
> process water (water for lab equipment, bunsen burners) during the 12-hour
> shutdown period..
>
>