Bldg. 26 - 3/18 - Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Mar 9 10:51:08 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451104A79@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dudley@mit.edu'" <dudley@MIT.EDU>,
        "'gfp170@mitrle.mit.edu'"
	 <gfp170@mitrle.mit.edu>,
        "'kates@mit.edu'" <kates@MIT.EDU>,
        "'ljtrudel@mit.edu'" <ljtrudel@MIT.EDU>, "'lsc@mit.edu'" <lsc@MIT.EDU>,
        "'radams@mit.edu'" <radams@MIT.EDU>,
        "'rmbesset@mit.edu'"
	 <rmbesset@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'trobins@mit.edu'"
	 <trobins@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 9 Mar 2000 10:46:48 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	dudley@mit.edu; gfp170@mitrle.mit.edu; kates@mit.edu;
> ljtrudel@mit.edu; lsc@mit.edu; radams@mit.edu; rmbesset@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu; trobins@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 26 - 3/18 - Shutdown Request
> 
> 
The following shutdown request for Bldg. 26 on Saturday, 3/18 is for your
information and comment.  Would you please let me know whether this does or
does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 26
> Date: 3/18/00
> Day: Saturday
> Time: 7 AM - 3 PM
> System: All hot and cold domestic and lab process water
> Duration: 8 hours
> Reason: 
> Replace two sections of drain line leaking in Room 26-051.
> 
> Effect: 
> Loss of all hot and cold domestic and lab process water.  This means that
> no toilets, bathroom, kitchen faucets, drinking fountains, emergency
> showers, or lab equipment requiring water to operate - will be operational
> during the shutdown period.
> 
> 