Bldg. 9 - 3/2 PM - 3/3 AM - Normal Electrical Power Shutdown Requ

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Feb 17 14:26:43 2000

Message-Id: <82F0D564C5ADD31180EF00508B55645110498B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'gallant@mit.edu'" <gallant@MIT.EDU>,
        "'jobrien@mit.edu'"
	 <jobrien@MIT.EDU>,
        "'mlavalle@mitvma.mit.edu'" <mlavalle@mitvma.mit.edu>,
        "'ndk@mit.edu'" <ndk@MIT.EDU>, "'randy@mit.edu'" <randy@MIT.EDU>,
        "'sexton@mit.edu'" <sexton@MIT.EDU>, "'src@mit.edu'" <src@MIT.EDU>,
        "'westlund@mit.edu'" <westlund@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>,
        "'dineend@mit.edu'"
	 <dineend@MIT.EDU>,
        "'engler@mit.edu'" <engler@MIT.EDU>,
        "'mshiffer@mit.edu'" <mshiffer@MIT.EDU>,
        "'mward@mit.edu'"
	 <mward@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 17 Feb 2000 14:23:13 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	gallant@mit.edu; jobrien@mit.edu; mlavalle@mitvma.mit.edu;
> ndk@mit.edu; randy@mit.edu; sexton@mit.edu; src@mit.edu; westlund@mit.edu;
> shutdowns@mit.edu; schedule@mit.edu; opsnote@mit.edu; dineend@mit.edu;
> engler@mit.edu; mshiffer@mit.edu; mward@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 9 - 3/2 PM - 3/3 AM - Normal Electrical Power Shutdown
> Request #2
> 
> 
The following normal electrical power shutdown request #2 for Bldg. 9 on
Thursday, 3/2 PM - Friday, 3/3 AM is for your information.  Would you please
let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 9
> Date: 3/2/03
> Day: Thursday
> Time: 11 PM (3/2) - 6:30 AM (3/3)
> System: Normal Electrical Power
> Duration: 7 hours
> Reason: 
> Cut in new high voltage switch.
> 
> Effect: 
> Loss of Power: Access controls, building power, elevators, computers,
> telephones, lighting, corridors/stairs;  Water:  hot domestic (water for
> bathroom and kitchen faucets) and heating hot water (heat);  Air:  supply
> ventilation (outside air), supply cooling, exhaust-laboratory,
> exhaust-general, exhaust-toilet and compressed control air.
> 
> 

home help back first fref pref prev next nref lref last post