Bldg. 3 - 140, 142, 144, 147 and Entire first floor - 2/29 - Shut

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Feb 17 10:41:26 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451104982@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'andreab@mit.edu'" <andreab@MIT.EDU>, "'dory@mit.edu'" <dory@MIT.EDU>,
        "'fenner@mit.edu'" <fenner@MIT.EDU>,
        "'gossard@mit.edu'"
	 <gossard@MIT.EDU>,
        "'ikec@mit.edu'" <ikec@MIT.EDU>,
        "'pmccosco@mit.edu'"
	 <pmccosco@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'sexton@mit.edu'" <sexton@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'mward@mit.edu'" <mward@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 17 Feb 2000 10:37:59 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	andreab@mit.edu; dory@mit.edu; fenner@mit.edu; gossard@mit.edu;
> ikec@mit.edu; pmccosco@mit.edu; schedule@mit.edu; sexton@mit.edu;
> shutdowns@mit.edu; mward@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 3 - 140, 142, 144, 147 and Entire first floor - 2/29 -
> Shutdown Request
> 
> 
The following shutdown request for Bldg. 3 - 140, 142, 144, 147 and Entire
first floor on Tuesday, 2/29 is for your review and comment.  Would you
please let me know whether this does or does not meet with your approval.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building:  3 - 140, 142, 144, 147 and Entire first floor 
> Date: 2/29/00
> Day: Tuesday
> Time: 7:30 AM - 3:30 PM
> System: Chilled Water
> Duration: 4 hours
> Reason: 
> To remove existing piping for old Fan Coil Unit - install new branch
> lines.
> 
> Effect: 
> Loss of chilled water in Building 3 for entire 1st floor during 4-hour
> shutdown period.
> 
> 