Bldg. 41 - 12/10 Electrical Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Dec 6 09:21:50 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD382@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'gallant@mit.edu'" <gallant@MIT.EDU>,
        "'pmccosco@mit.edu'"
	 <pmccosco@MIT.EDU>,
        "'brisson@mit.edu'" <brisson@MIT.EDU>,
        "'jlsmith@mit.edu'" <jlsmith@MIT.EDU>,
        "'delsemil@mit.edu'"
	 <delsemil@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'opsnote@mit.edu'"
	 <opsnote@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 6 Dec 1999 09:20:51 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	gallant@mit.edu; pmccosco@mit.edu; brisson@mit.edu; jlsmith@mit.edu;
> delsemil@mit.edu; shutdowns@mit.edu; schedule@mit.edu; opsnote@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 41 - 12/10 Electrical Power Shutdown Request
> 
> 
The following electrical power shutdown request for Bldg. 41 on Friday,
12/10 is for your review and comment.  Would you please let me know whether
this does or does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 41
> Date: 12/10/99
> Day: Friday
> Time: 3 AM - 7 AM
> System: Normal Electrical Power
> Duration: 4 hours
> Reason: 
> Add temporary power for trailer.
> 
> Effect: 
> Loss of Power:  building power, eleveators, computers, telephones,
> lighting, corridor/stairway lighting;  Water:  chilled water (air
> conditioning);  Air:  Supply ventilation, supply cooling, supply heating,
> exhaust laboratory, exhaust-general, exhaust-toilet, compressed control,
> compressed lab air and lab vacuum air;  Steam:  condensate return.
> 
> 