[49398] in Hotline Meeting
Bldgs. 2, 3, 4 and 10 - 12/4 - Critical Shutdown Request To Be Re
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Dec 2 14:26:34 1999
Message-Id: <D8716484935DD311A1C30008C75B07F90AD36B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
"'duggins@math.mit.edu'" <duggins@math.mit.edu>,
"'tivon@math.mit.edu'"
<tivon@math.mit.edu>,
"'akelsey@mit.edu'" <akelsey@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
"'wjfitz@mit.edu'" <wjfitz@MIT.EDU>,
"'jhlyons@mit.edu'" <jhlyons@MIT.EDU>,
"'graham@mit.edu'"
<graham@MIT.EDU>,
"'ccarey@mit.edu'" <ccarey@MIT.EDU>, "'krf@mit.edu'"
<krf@MIT.EDU>,
"'jcentor@mit.edu'" <jcentor@MIT.EDU>,
"'dineend@mit.edu'" <dineend@MIT.EDU>, "'frc@mit.edu'" <frc@MIT.EDU>,
"'griffin@mit.edu'" <griffin@MIT.EDU>,
"'naylor@mit.edu'"
<naylor@MIT.EDU>,
"'rrhonda@mit.edu'" <rrhonda@MIT.EDU>,
"'mleen@mit.edu'" <mleen@MIT.EDU>,
"'sandylo@mit.edu'" <sandylo@MIT.EDU>,
"'jfucillo@mit.edu'" <jfucillo@MIT.EDU>,
"'menos@mit.edu'"
<menos@MIT.EDU>,
"'jobrien@mit.edu'" <jobrien@MIT.EDU>,
"'dory@mit.edu'"
<dory@MIT.EDU>,
"'pmccosco@mit.edu'" <pmccosco@MIT.EDU>,
"'tetaylor@mit.edu'" <tetaylor@MIT.EDU>,
"'archall@mit.edu'"
<archall@MIT.EDU>,
"'mamullow@mit.edu'" <mamullow@MIT.EDU>,
"'nddk@mit.edu'" <nddk@MIT.EDU>, "'fenner@mit.edu'" <fenner@MIT.EDU>,
"'sdimond@mit.edu'" <sdimond@MIT.EDU>,
"'sexton@mit.edu'"
<sexton@MIT.EDU>, "'rks@mit.edu'" <rks@MIT.EDU>,
"'mward@mit.edu'"
<mward@MIT.EDU>,
"'granvill@mit.edu'" <granvill@MIT.EDU>,
"'mibs@eecs.mit.edu'" <mibs@eecs.mit.edu>,
"'otten@mit.edu'"
<otten@MIT.EDU>, "'kates@mit.edu'" <kates@MIT.EDU>,
"'trobins@mit.edu'"
<trobins@MIT.EDU>, "'jdb@mit.edu'" <jdb@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 2 Dec 1999 14:25:41 -0500
Mime-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Dear Everyone:
It has been requested that the following Critical shutdown request for
Bldgs. 2, 3, 4 and 10 initially for Saturday, December 4 be rescheduled to
Sunday, December 5. Would you please let me know whether this new date and
time better fits your schedules.
Thanks very much for your time and I look forward to hearing from you.
Andrea Nichols
Operations Center
8-7872
Status: Critical
Building: 2, 3, 4 and 10
Date: 12/5/99
Day: Sunday
Time: 4 AM - 4 PM or 6 AM - 6 PM
System: Low Pressure Steam
Duration: 12 hours
Reason: Repair/replace 10" heating main line which is leaking
Effect: Loss of low pressure steam. This means there will be no heat
available in the above listed buildings. According to the weather
forecasters, it is supposed to be 55 - 60 degrees on Sunday.