[49392] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. E10 - 12/2 - All Bathrooms Emergency Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Dec 2 07:59:34 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD362@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cpomiecko@mit.edu'" <cpomiecko@MIT.EDU>,
        "'gallant@mit.edu'"
	 <gallant@MIT.EDU>,
        "'nlowe@mit.edu'" <nlowe@MIT.EDU>, "'jharr@mit.edu'"
	 <jharr@MIT.EDU>,
        "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'" <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'"
	 <jfreeman@MIT.EDU>,
        Stephen McHugh <smchugh@PLANT.MIT.EDU>, E-Zone
	 <E-Zone@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>
Date: Thu, 2 Dec 1999 07:59:05 -0500 
Mime-Version: 1.0
Content-Type: text/plain

> To: 	cpomiecko@mit.edu; gallant@mit.edu; nlowe@mit.edu; jharr@mit.edu;
> dcarlson@mit.edu; cappucci@mit.edu; jfreeman@mit.edu; Stephen McHugh;
> E-Zone; mmahoney@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; shutdowns@mit.edu
> Subject: 	Bldg. E10 - 12/2 -  All Bathrooms Emergency Shutdown
> 
> 
The following Emergency shutdown for Bldg. E10 for today (Thursday, 12/2) is
for your information.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Emergency
> Building: E10 - Bathrooms
> Date: 12/2/99
> Day: Thursday
> Time: 8 AM - 3 PM
> System: Hot Domestic and Cold Domestic Water
> Duration: 7 hours
> Reason: 
> All bathroms must be repaired - toilets do not work, flushometers must be
> replaced, sink faucets not operational.
> 
> Effect: 
> Loss of all bathrooms in Bldg. E10 during 7-hour shutdown period.
> Building E15 is the closest building where there are bathrooms.
> 
> 