[49346] in Hotline Meeting
Bldg. 10 - 11/30 - Emergency Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 30 11:34:32 1999
Message-Id: <D8716484935DD311A1C30008C75B07F90AD344@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'rrhonda@mit.edu'" <rrhonda@MIT.EDU>,
"'otten@mit.edu'" <otten@MIT.EDU>,
"'alexnow@mit.edu'" <alexnow@MIT.EDU>,
"'sexton@mit.edu'" <sexton@MIT.EDU>, "'mleen@mit.edu'" <mleen@MIT.EDU>,
"'mward@mitvmc.mit.edu'" <mward@mitvmc.mit.edu>,
"'rks@mit.edu'"
<rks@MIT.EDU>, "'archall@mit.edu'" <archall@MIT.EDU>,
"'jdb@mit.edu'"
<jdb@MIT.EDU>, "'kates@mit.edu'" <kates@MIT.EDU>,
"'trobins@mit.edu'"
<trobins@MIT.EDU>,
"'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'" <cappucci@MIT.EDU>,
"'jfreeman@mit.edu'"
<jfreeman@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, C-Zone
<C-Zone@MIT.EDU>,
Billy Homeyer <whomeyer@PLANT.MIT.EDU>,
"Larry St. John" <lstjohn@PLANT.MIT.EDU>,
"'dcarlson@mit.edu'"
<dcarlson@MIT.EDU>,
"'cappucci@mit.edu'" <cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'mmahoney@mit.edu'"
<mmahoney@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>
Date: Tue, 30 Nov 1999 11:34:00 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: schedule@mit.edu; shutdowns@mit.edu; rrhonda@mit.edu; otten@mit.edu;
> alexnow@mit.edu; sexton@mit.edu; mleen@mit.edu; mward@mitvmc.mit.edu;
> rks@mit.edu; archall@mit.edu; jdb@mit.edu; kates@mit.edu; trobins@mit.edu;
> dcarlson@mit.edu; cappucci@mit.edu; jfreeman@mit.edu; mmahoney@mit.edu;
> C-Zone; Billy Homeyer; Larry St. John; dcarlson@mit.edu; cappucci@mit.edu;
> jfreeman@mit.edu; mmahoney@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldg. 10 - 11/30 - Emergency Shutdown
>
>
The following Emergency shutdown for Bldg. 10 beginning now (11/30) is for
your information.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: 10
> Date: 11/30/99
> Day: Tuesday
> Time: 11:15 AM - 1:15 PM
> System: Low Pressure Steam
> Duration: 2 hours
> Reason:
> Pipe needs to be repaired
>
> Effect:
> Loss of heat in Bldg. 10 during 2-hour shutdown.
>
>