Bldg. E52 - 055 A & B - 11/j29 - 12/1 - Emergency Asbestos Remova
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 29 09:46:18 1999
Message-Id: <D8716484935DD311A1C30008C75B07F90AD32F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jbkalb@mit.edu'" <jbkalb@MIT.EDU>,
"'mscoppa@mit.edu'"
<mscoppa@MIT.EDU>,
"'michaela@mit.edu'" <michaela@MIT.EDU>, "'gwj@mit.edu'" <gwj@MIT.EDU>,
E-Zone <E-Zone@MIT.EDU>, "'tr6@mit.edu'"
<tr6@MIT.EDU>,
"'jdcouett@mit.edu'" <jdcouett@MIT.EDU>,
"'tdoyle@mit.edu'" <tdoyle@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>
Date: Mon, 29 Nov 1999 09:45:54 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: jbkalb@mit.edu; mscoppa@mit.edu; michaela@mit.edu; gwj@mit.edu;
> E-Zone; tr6@mit.edu; jdcouett@mit.edu; tdoyle@mit.edu; shutdowns@mit.edu;
> schedule@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldg. E52 - 055 A & B - 11/j29 - 12/1 - Emergency Asbestos
> Removal Notification
>
>
The following emergency abestos removal notification for Bldg. E52 - 055A
and 055A from Monday, 11/29 thru Wednesday, 12/1 is for your information.
If you have any questions about this, please contact Tammy Doyle at 3-5166.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: E52 - 055 A & B
> Date: 11/29/01
> Day: Monday
> Time: 11/29 (7 AM) - 12/1 (4PM)
> System: None - asbestos removal notification
> Duration: 57 hours
> Reason:
> Remove 10 square feet of asbestos which is throughout the corridor.
>
> Effect:
> No access to area where asbestos is being removed - this will be cordoned
> off.
>
>