Bldg. 2 - 10/22 - Critical Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 20 11:46:12 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD18C@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'ndpope@mit.edu'" <ndpope@MIT.EDU>,
        "'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
        "'tivon@math.mit.edu'"
	 <tivon@math.mit.edu>,
        "'mbj@mit.edu'" <mbj@MIT.EDU>, "'akelsey@mit.edu'"
	 <akelsey@MIT.EDU>,
        "'wjfitz@mit.edu'" <wjfitz@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 20 Oct 1999 11:39:26 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	schedule@mit.edu; shutdowns@mit.edu; ndpope@mit.edu;
> capozzi@math.mit.edu; tivon@math.mit.edu; mbj@mit.edu; akelsey@mit.edu;
> wjfitz@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 2 - 10/22 - Critical Shutdown Request
> 
> 
The following Critical shutdown request for Bldg. 2 on Friday, 10/22 is for
your information and comment.  Would you please let me know whether this
does or does not have your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872	


> Status: Critical
> Building: 2
> Date: 10/22/99
> Day: Friday
> Time: 9 AM - 5 PM
> System: medium pressure steam, supply heating, hot domestic water
> Duration: 8 hours
> Reason: 
> On the Walker main - replace leaking tee and 90 degree elbow
> 
> Effect: 
> Loss of supply heating (via air handlers)  in all rooms that have air
> handler units; loss of hot domestic water in all bathroom, kitchen and lab
> faucets 
> 
> 