Bldg. 1-267, 167, 265, 267, 367 & 3rd floor - 10/18 Now Reschedu

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Oct 18 09:57:29 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD15C@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dfucillo@mit.edu'" <dfucillo@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'mgowen@mit.edu'" <mgowen@MIT.EDU>,
        "'mamullow@mit.edu'" <mamullow@MIT.EDU>,
        "'mgibson@mit.edu'"
	 <mgibson@MIT.EDU>,
        "'patdixon@mit.edu'" <patdixon@MIT.EDU>,
        "'pmccocso@mit.edu'" <pmccocso@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'scottc@mit.edu'" <scottc@MIT.EDU>,
        "'skanode@mit.edu'" <skanode@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
        Frank Lewis <flewis@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 18 Oct 1999 09:50:53 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	dfucillo@mit.edu; shutdowns@mit.edu; mgowen@mit.edu;
> mamullow@mit.edu; mgibson@mit.edu; patdixon@mit.edu; pmccocso@mit.edu;
> schedule@mit.edu; scottc@mit.edu; skanode@mit.edu; C-Zone; Frank Lewis
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 1-267, 167, 265, 267, 367 & 3rd floor - 10/18  Now
> Rescheduled to 10/21- Shutdown Request
> 
> 
The following shutdown did not occur this morning. The Project Manager has
asked if this could be rescheduled to this coming Thursday, 10/21.

Would you please let me know if this new date would meet with your approval
or would not.

Thanks again.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building:  1-267, 167, 265, 267, 367 & 3rd floor 
> Date: 10/21/99
> Day: Thursday
> Time: 7 AM - 3 PM
> System: Cold Domestic Water
> Duration: 8 hours
> Reason: 
> To remove and replace existing old supply shutoff valve ith new ball
> valve.
> 
> Effect: 
> Loss of  cold domestic water.  This means that no toilets, bathroom,
> kitchen faucets or drinking fountains will be operational during the
> 8-hour shutdown period. The toilets in Building 2 and other area buildings
> will be operating however.
> 
> 