[48734] in Hotline Meeting
Bldg. E53 - 10/19 - Filter Change/Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 8 11:24:40 1999
Message-Id: <D8716484935DD311A1C30008C75B07F90AD0FF@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'lhill@mit.edu'" <lhill@MIT.EDU>, "'crf@mit.edu'"
<crf@MIT.EDU>,
"'michaela@mit.edu'" <michaela@MIT.EDU>,
"'mscoppa@mit.edu'" <mscoppa@MIT.EDU>,
"'janets@mit.edu'"
<janets@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 8 Oct 1999 11:18:09 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: schedule@mit.edu; shutdowns@mit.edu; lhill@mit.edu; crf@mit.edu;
> michaela@mit.edu; mscoppa@mit.edu; janets@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E53 - 10/19 - Filter Change/Shutdown Request
>
>
The following filter change/shutdown request for Bldg. E53 on Tuesday, 10/19
is for your information and comment. Would you please let me know whether
this does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E53
> Date: 10/19/99
> Day: Tuesday
> Time: 7 AM - 12:30 PM
> System: Supply Fan 1 (supply ventilation, supply cooling and supply
> heating)
> Duration: 5 1/2 hours
> Reason:
> Change bag filters on Supply Fan 1 which is located in 068 MR.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating during 5 1/2
> hour period.
>
>