[48680] in Hotline Meeting
Bldg. 2 - 017 (and rest of bldg.) 10/14 PM - 10/15 AM - Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Oct 4 13:08:09 1999
Message-Id: <D8716484935DD311A1C30008C75B07F90AD0C6@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'akelsey@mit.edu'" <akelsey@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
"'cappozzi@math.mit.edu'" <cappozzi@math.mit.edu>,
"'duggins@math.mit.edu'" <duggins@math.mit.edu>,
"'jhlyons@mit.edu'"
<jhlyons@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 4 Oct 1999 13:01:36 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: 'akelsey@mit.edu'; 'mbj@mit.edu'; 'cappozzi@math.mit.edu';
> 'duggins@math.mit.edu'; 'jhlyons@mit.edu'; 'schedule@mit.edu';
> 'shutdowns@mit.edu'
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 2 - 017 (and rest of bldg.) 10/14 PM - 10/15 AM -
> Shutdown Request (Electrical 400 AMP I-Line Panel
>
>
Dear Everyone:
It has been requested that the above shutdown begin later than 9 PM on
10/14. Would you please let me know if the new time (10 PM - 6 AM) meets
with your approval or does not.
Thanks again.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: Bldg. 2 - 017 (and rest of bldg.) 10/14 PM - 10/15 AM - Shutdown
> Request (Electrical 400 AMP I-Line Panel
> Date: 10/14/15
> Day: Thursday
> Time: 10 PM (10/14) - 6 AM (10/15)
> System: Elecrical 400 aMP I-Line Panel
> Duration: 8 hours
> Reason:
> Relocate panel to back wall of electric room (017) - refeed from new
> switch board.
>
> Effect:
> Loss of Power: Access controls, building power; Water: chilled water
> (air conditioning), condenser water, hot domestic and hot lab process
> water; cold domestic and cold lab process water and heating hot water;
> Air: supply ventilation, supply cooling, exhaust laboratory, exhaust
> toilet, compressed control, compressed lab air, lab vacuum air and make up
> air for Chemistry exhaust hoods and make-up air in Chemistry labs.
> Rooms that will lose power (480V) are: 2-206 (disconnected already - new
> feed in place), 2-211, 2-007 - (2 lasers will be off line), 2 - Fan on
> Roof not running at this time; 4-082 - transformer will be offline; 4-070
> - transformer will be offline; 2-006 machine room.
> Will be off - Air Handler 1 - booster pump - hot water - P3 & P2 chilled
> water; Air Handler 2 - condensate pump - air compressor for Building Air.
>
> Air Handler units for all of Building 2 will be offline.
>
>
>
>