[48657] in Hotline Meeting
W20 - 5fh floor - Corridor only 10/1 - Emergency Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 1 10:31:34 1999
Message-Id: <D8716484935DD311A1C30008C75B07F90AD0AC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mwf@mit.edu'" <mwf@MIT.EDU>, "'pwalsh@mit.edu'" <pwalsh@MIT.EDU>,
"'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 1 Oct 1999 10:25:13 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: 'mwf@mit.edu'; 'pwalsh@mit.edu'; 'dcarlson@mit.edu';
> 'cappucci@mit.edu'; 'jfreeman@mit.edu'; 'mmahoney@mit.edu'; D-Zone;
> 'shutdowns@mit.edu'
> Cc: shutdown@plant.mit.edu
> Subject: W20 - 5fh floor - Corridor only 10/1 - Emergency Shutdown
>
>
The following emergency shutdown for Bldg. W20 - 5th floor corridor only on
Friday, 10/1 is for your information.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: W20 - 5fh floor - Corridor Only
> Date: 10/1/99
> Day: Friday
> Time: 7 AM - 3 PM
> System: Air Handler 8
> Duration: 8 hours
> Reason:
> Repair leak in coils of Air Handler 8.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in W20 - 5th
> floor corridors only. All other areas will continue to have air flow. Rm.
> 575 and the computer room have their own air systems.
>
>