E23 - 9/28 - Critical Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Sep 27 08:08:10 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90AD061@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'avel@med.mit.edu'" <avel@med.mit.edu>,
        "'bengel@mit.edu'"
	 <bengel@MIT.EDU>,
        "'cobb@ai.mit.edu'" <cobb@ai.mit.edu>,
        "'edwa@med.mit.edu'" <edwa@med.mit.edu>,
        "'roge@med.mit.edu'"
	 <roge@med.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 27 Sep 1999 08:01:57 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	avel@med.mit.edu; bengel@mit.edu; cobb@ai.mit.edu; edwa@med.mit.edu;
> roge@med.mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	E23 -  9/28 - Critical Shutdown Request
> 
> 
The following Critical shutdown request for Bldg. E23 on Tuesday, 9/28 is
for your review and comment.  Would you please let me know whether this does
or does not meet with your approval. 

Thanks.

Andrea Nichols
Operations Center
8-7872

> Status: Critical
> Building: E23
> Date: 9/28/99
> Day: Tuesday
> Time: 5 AM - 7 AM
> System: Air Handlers 8, 9, 10 and 11
> Duration: 2 hours
> Reason: 
> To clean intake of fans for Joint Community inspection.
> 
> Effect: 
> Loss of supply ventilation, supply cooling, supply heating and exhaust
> general air in all of E23 including the hospital and atrium areas.
> 
> 