FW: Bldg. 2 - Campus CWS & CWR - Approved 9/2-3 - Shutdown Reques

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 3 07:01:29 1999

Message-Id: <D8716484935DD311A1C30008C75B07F90ACF59@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: 'akelsey@mit.edu', 'mbj@mit.edu', 'schedule@mit.edu', 'shutdowns@mit.edu',
        'duggins@math.mit.edu', 'cappozzi@math.mit.edu',
        'daisymae@math.mit.edu', 'wjfitz@mit.edu'
Cc: "'shutdowns@plant.mit.edu'" <shutdowns@plant.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Date: Fri, 3 Sep 1999 06:55:40 -0400 
Mime-Version: 1.0
Content-Type: text/plain

Dear Everyone:
The following message from Billy Homeyer concerning the above shutdown for
yesterday and this morning is for your information.

Andrea Nichols
Operations Center
8-7872

----------
From:  Billy Homeyer
Sent:  Friday, September 03, 1999 6:20 AM
To:  shutdown@plant.mit.edu; <mailto:shutdown@plant.mit.edu;>
rm-shutdown@mit.edu <mailto:rm-shutdown@mit.edu> 
Cc:  Andrea Nichols; Joe Collins; Paul Rudack
Subject:  FW: Bldg. 2 - Campus CWS & CWR - Approved 9/2-3 - Shutdown Request
Importance:  High

Good Morning, 

	Due to unforeseen circumstances, this shutdown has been extended
until 9AM this morning.  The contractors are just now finishing up the last
few pipe welds (6:30AM). So please be patient.

				Billy Homeyer  C-Zone

----------
From: 	Gerry Desmond
Sent: 	Friday, September 03, 1999 6:12 AM
To: 	Billy Homeyer
Subject: 	FW: Bldg. 2 - Campus CWS & CWR - Approved 9/2-3 - Shutdown
Request
Importance: 	High



----------
From: 	Andrea Nichols[SMTP:andrea@PLANT.MIT.EDU]
<mailto:[SMTP:andrea@PLANT.MIT.EDU]> 
Sent: 	Thursday, September 02, 1999 7:00 AM
To: 	RM-2ndShift; RM-3rdShift; 'dcarlson@mit.edu'; 'cappucci@mit.edu';
'jfreeman@mit.edu'; 'mmahoney@mit.edu'; C-Zone; Billy Homeyer; Gerry
Desmond; 'jcollins@mit.edu'; Howard  Harrison
Cc: 	'shutdown@plant.mit.edu'; 'rm-shutdown@mit.edu'
Subject: 	Bldg. 2 - Campus CWS & CWR - Approved 9/2-3 - Shutdown
Request
Importance: 	High

> To: 	RM-2ndShift; RM-3rdShift; dcarlson@mit.edu;
<mailto:dcarlson@mit.edu;>  cappucci@mit.edu; <mailto:cappucci@mit.edu;> 
> jfreeman@mit.edu; <mailto:jfreeman@mit.edu;>  mmahoney@mit.edu;
<mailto:mmahoney@mit.edu;>  C-Zone; Billy Homeyer; Gerry Desmond;
> jcollins@mit.edu; <mailto:jcollins@mit.edu;>  Howard  Harrison
> Cc: 	shutdown@plant.mit.edu; <mailto:shutdown@plant.mit.edu;>
rm-shutdown@mit.edu <mailto:rm-shutdown@mit.edu> 
> Subject: 	Bldg. 2 - Campus CWS & CWR - Approved 9/2-3 - Shutdown
> Request
> 
> 
The following approved shutdown request for Bldg. 2 - Campus CWS and WR for
this evening (9/2) to tomorrow morning (9/3) is for your information.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 2
> Date: 9/2/03
> Day: Thursday
> Time: 3 PM (9/2) - 9 AM (9/3)
> System: Chilled Water/Supply Cooling/smoke detectors
> Duration: 18 hours
> Reason: 
> Cut in Chilled water supply and chilled water return for laser lab
> renovation.
> 
> Effect: 
> Loss of chilled water (air conditioning) and supply cooling (cooling)
> during 10-hour shutdown. Also loss of smoke detectors (shutdown when
> welding occurs).
> 
> 