[48336] in Hotline Meeting
Bldgs. W13 (Bexley Hall) and W15 (the Chapel) - 9/3 - Electrical
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Aug 31 08:58:16 1999
Message-Id: <D8716484935DD311A1C30008C75B07F90ACF24@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mwhelan@mit.edu'" <mwhelan@MIT.EDU>, "'mwf@mit.edu'" <mwf@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 31 Aug 1999 08:52:32 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: mwhelan@mit.edu; mwf@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. W13 (Bexley Hall) and W15 (the Chapel) - 9/3 -
> Electrical Shutdown Request
>
>
The following electrical shutdown request for W13 (Bexley Hall) and W15 (The
Chapel) on Friday, 9/3 is for your review and comment. Would you please let
me know whether this does or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: W13 (Bexley Hall) and W15 (The Chapel)
> Date: 9/3/99
> Day: Friday
> Time: 6 AM - 2 PM
> System: Electrical
> Duration: 8 hours
> Reason:
> Tie in permanent service.
>
> Effect:
> Loss of Power: access controls, building power, computers and lighting;
> Water: Hot domestic water; Air: exhaust general and exhaust toilet air.
>
>