[48236] in Hotline Meeting
Bldg. 1 - 153, 163, 163A and 165 - 8/21 - Electrical Shutdown Req
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 18 13:14:09 1999
Message-Id: <9D3AC86A7244D311919900805FBE000006AE52@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patdixon@mit.edu'" <patdixon@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 18 Aug 1999 13:11:46 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: patdixon@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 1 - 153, 163, 163A and 165 - 8/21 - Electrical
> Shutdown Request
>
>
The following electrical shutdown request for Bldg. 1 - 153, 163, 16A and
165 on Saturday, 8/21 is for your information. Would you please let me know
whether this does or does not meet with your approval.
Thank you Pat.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 1-153, 163, 163A and 165 only
> Date: 8/21/99
> Day: Saturday
> Time: 6 AM - 4 PM
> System: Electrical
> Duration: 10 hours
> Reason:
> Rework of conduit and branch circuits/conflicts in new HVAC ductwork.
>
> Effect:
> Loss of receptacle power in Bldg. 1 - 153, 163, 163A and 165 only. This
> means that any computers, lamps or anything else plugged into a receptacle
> in the above listed rooms will not operate during this shutdown.
>
>