[48236] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 1 - 153, 163, 163A and 165 - 8/21 - Electrical Shutdown Req

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 18 13:14:09 1999

Message-Id: <9D3AC86A7244D311919900805FBE000006AE52@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patdixon@mit.edu'" <patdixon@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 18 Aug 1999 13:11:46 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	patdixon@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 1 - 153, 163, 163A and 165 - 8/21 - Electrical
> Shutdown Request
> 
> 
The following electrical shutdown request for Bldg. 1 - 153, 163, 16A and
165 on Saturday, 8/21 is for your information.  Would you please let me know
whether this does or does not meet with your approval.

Thank you Pat.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 1-153, 163, 163A and 165 only
> Date: 8/21/99
> Day: Saturday
> Time: 6 AM - 4 PM
> System: Electrical
> Duration: 10 hours
> Reason: 
> Rework of conduit and branch circuits/conflicts in new HVAC ductwork.
> 
> Effect: 
> Loss of receptacle power in Bldg. 1 - 153, 163, 163A and 165 only. This
> means that any computers, lamps or anything else plugged into a receptacle
> in the above listed rooms will not operate during this shutdown.
> 
> 