Bldgs. W13 and W15 - 8/13 - Critical Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Aug 10 13:15:29 1999
Message-Id: <9D3AC86A7244D311919900805FBE000006ADDB@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mwhelan@mit.edu'" <mwhelan@MIT.EDU>, "'pdc@mit.edu'" <pdc@MIT.EDU>,
"'mwf@mit.edu'" <mwf@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 10 Aug 1999 13:13:16 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: mwhelan@mit.edu; pdc@mit.edu; mwf@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. W13 and W15 - 8/13 - Critical Shutdown Request
>
>
The following Critical shutdown request for Bldgs. W13 and W15 on Friday,
8/13 is for your information and comment.
Would you please let me know whether this has your approval or does not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: W13 and W15
> Date: 8/13/99
> Day: Friday
> Time: 10 AM - 12 Noon
> System: Electrical Power
> Duration: 2 hours
> Reason:
> Renovations to electrical service.
>
> Effect:
> Loss of Power: building power, computers and lighting.
>
>