[48045] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 1 and Bldg. 3 - 169 (Utility Mechanics Room) - 8/5 PM - 8/

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jul 30 15:11:40 1999

Message-Id: <9D3AC86A7244D311919900805FBE000006AD3B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mgibson@mit.edu'" <mgibson@MIT.EDU>,
        "'patdixon@mit.edu'"
	 <patdixon@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'pmccosco@mit.edu'"
	 <pmccosco@MIT.EDU>,
        "'fenner@mit.edu'" <fenner@MIT.EDU>, C-Zone
	 <C-Zone@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 30 Jul 1999 15:09:46 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	mgibson@mit.edu; patdixon@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu; pmccosco@mit.edu; fenner@mit.edu; C-Zone
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 1  and Bldg. 3 - 169 (Utility Mechanics Room) - 8/5 PM
> - 8/6 AM Shutdown Request
> 
> 
The following shutdown request for Bldg. 1 and Bldg. 3 - 1690 on 8/5 PM and
8/6 AM is for  your information and comment.  Would you please let me know
whether this does or does not meet with your approval.

Thanks again.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: Bldg. 1 and Blsg. 3 - 169
> Date: 8/5/06
> Day: Thursday
> Time: 6 PM (8/5) - 6 AM (8/6)
> System: Electrical Service/fluid drive machine
> Duration: 12 hours
> Reason: 
> Conduit run conflicts with new.
> 
> Effect: 
> Loss of building power in Building 1 and fluid drive machine in 3-169 only
> during shutdown period.
> 
> 

home help back first fref pref prev next nref lref last post