[47860] in Hotline Meeting
Bldg. 4 - All - 7/9 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jun 30 11:14:21 1999
Message-Id: <ECFE33C8A3D4D111917900805FBE00008319AA@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'ccarey@mit.edu'" <ccarey@MIT.EDU>,
"'cwilkes@mit.edu'"
<cwilkes@MIT.EDU>, "'frc@mit.edu'" <frc@MIT.EDU>,
"'graham@mit.edu'"
<graham@MIT.EDU>,
"'jcentor@mit.edu'" <jcentor@MIT.EDU>,
"'jfucillo@mit.edu'" <jfucillo@MIT.EDU>,
"'lechtman@mit.edu'"
<lechtman@MIT.EDU>,
"'lpaul@mit.edu'" <lpaul@MIT.EDU>, "'mbj@mit.edu'"
<mbj@MIT.EDU>,
"'mibs@eecs.mit.edu'" <mibs@eecs.mit.edu>,
"'preacher@mit.edu'" <preacher@MIT.EDU>,
"'rmbesset@mit.edu'"
<rmbesset@MIT.EDU>,
"'rrhonda@mit.edu'" <rrhonda@MIT.EDU>,
"'sandylo@mit.edu'" <sandylo@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'seyferth@wccf.mit.edu'" <seyferth@wccf.mit.edu>,
"'smithmt@mit.edu'" <smithmt@MIT.EDU>,
"'sralston@mit.edu'"
<sralston@MIT.EDU>,
"'strehle@mit.edu'" <strehle@MIT.EDU>,
"'trapaga@mit.edu'" <trapaga@MIT.EDU>,
"'akelsey@mit.edu'"
<akelsey@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 30 Jun 1999 11:06:30 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: ccarey@mit.edu; cwilkes@mit.edu; frc@mit.edu; graham@mit.edu;
> jcentor@mit.edu; jfucillo@mit.edu; lechtman@mit.edu; lpaul@mit.edu;
> mbj@mit.edu; mibs@eecs.mit.edu; preacher@mit.edu; rmbesset@mit.edu;
> rrhonda@mit.edu; sandylo@mit.edu; schedule@mit.edu; seyferth@wccf.mit.edu;
> smithmt@mit.edu; sralston@mit.edu; strehle@mit.edu; trapaga@mit.edu;
> akelsey@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 4 - All - 7/9 - Shutdown Request
>
>
The following shutdown request for Bldg. 4 - All on 7/9 is for your review
and comment. Would you please let me know whether this does or does not
meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 4
> Date: 7/9/99
> Day: Friday
> Time: 4 AM - 7 AM
> System: Electrical Closet - 4-050E
> Duration: 3 hours
> Reason:
> To research breakers and wire sizes for future shutdown.
>
> Effect:
> Loss of Power: buildng power, computers; Water: chilled water (air
> conditioning); Air: supply ventilation (general air), supply cooling,
> exhaust-general air and exhaust-toilet air; during 3-hour shutdown period.
>
>