Bldg. 1 - 044 & Rest of Building - 6/28 - Shutdown Request Now Re

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 25 13:36:31 1999

Message-Id: <ECFE33C8A3D4D111917900805FBE0000831974@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'fenner@mit.edu'"
	 <fenner@MIT.EDU>,
        "'magowen@mit.edu'" <magowen@MIT.EDU>,
        "'mamullow@mit.edu'" <mamullow@MIT.EDU>,
        "'mgibson@mit.edu'"
	 <mgibson@MIT.EDU>,
        "'patdixon@mit.edu'" <patdixon@MIT.EDU>,
        "'pmccosco@mit.edu'" <pmccosco@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'scottc@mit.edu'" <scottc@MIT.EDU>,
        "'skanode@mit.edu'" <skanode@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
        "'jcollins@mit.edu'"
	 <jcollins@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
        Billy Homeyer
	 <whomeyer@PLANT.MIT.EDU>,
        Gerry Desmond <gdesmond@PLANT.MIT.EDU>
Date: Fri, 25 Jun 1999 13:28:54 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	shutdowns@mit.edu; fenner@mit.edu; magowen@mit.edu;
> mamullow@mit.edu; mgibson@mit.edu; patdixon@mit.edu; pmccosco@mit.edu;
> schedule@mit.edu; scottc@mit.edu; skanode@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; jcollins@mit.edu;
> C-Zone; Billy Homeyer; Gerry Desmond
> Subject: 	Bldg. 1 - 044 & Rest of Building - 6/28 - Shutdown Request
> Now Rescheduled to 7/1PM - 7/2 AM
> 
> 
Dear Everyone:
I have been informed that the above shutdown request originally for 6/28 has
now been rescheduled to 7/1 PM - 7/2 AM. This work will be combined with the
chilled water system shutdown for Bldg. 1 (changing existing 4" main to 6"
second floor to the first floor).

If you have any questions about this, please contact Mr. Joe Collins at
3-3621.
Would you please let me know whether this combined work has your approval or
does not.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 1 - 044 & rest of building
> Date: 7/1/02
> Day: Thursday
> Time: 6 PM (7/1) - 6 AM (7/2)
> System: Chilled Water
> Duration: 12 hours
> Reason: 
> changing existing 4" main to 6" second floor to the first floor - remove
> olf pumps and tie in new valve for future work.
> 
> Effect: 
> Loss of chilled water (air conditioning) in all of Bldg. 1 during the
> shutdown period.
> 
> 