Bldg. 1 - 7/1 and 2 - Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 25 07:48:24 1999
Message-Id: <ECFE33C8A3D4D111917900805FBE0000831967@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'magowen@mit.edu'" <magowen@MIT.EDU>,
"'mamullow@mit.edu'"
<mamullow@MIT.EDU>,
"'mgibson@mit.edu'" <mgibson@MIT.EDU>,
"'patdixon@mit.edu'" <patdixon@MIT.EDU>,
"'pmccosco@mit.edu'"
<pmccosco@MIT.EDU>,
"'fenner@mit.edu'" <fenner@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'scottc@mit.edu'"
<scottc@MIT.EDU>,
"'skanode@mit.edu'" <skanode@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>
Date: Fri, 25 Jun 1999 07:40:43 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: magowen@mit.edu; mamullow@mit.edu; mgibson@mit.edu;
> patdixon@mit.edu; pmccosco@mit.edu; fenner@mit.edu; schedule@mit.edu;
> scottc@mit.edu; skanode@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldg. 1 - 7/1 and 2 - Chilled Water Shutdown Request
>
>
The following chilled water request for Bldg. 1 on 7/1 and 7/2 is for your
review and comment. Would you please let me know whether this does or does
not have your approval.
Thank youl
Andrea Nichols
Operation Center
8-7872
> Status: Normal
> Building: 1
> Date: 7/1/02
> Day: Thursday
> Time: 6 PM (7/1) - 6 AM (7/2)
> System: Chilled Water
> Duration: 12 hours
> Reason:
> Changing existing 4" main pipe to 6" pipe on the second floor to the first
> floor.
>
> Effect:
> Loss of chilled water (air conditioning) during the shutdown period.
>
>