[47790] in Hotline Meeting
Rescheduled Again - Bldg. E19 - 6th and 7th Floors Shutdown Reque
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jun 22 11:42:27 1999
Message-Id: <ECFE33C8A3D4D111917900805FBE000083192F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'barrett@mit.edu'" <barrett@MIT.EDU>,
"'cashaw@mit.edu'"
<cashaw@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'esico@mit.edu'" <esico@MIT.EDU>,
"'sfalconi@mit.edu'"
<sfalconi@MIT.EDU>,
"'honiker@mit.edu'" <honiker@MIT.EDU>,
"'kelley@mit.edu'" <kelley@MIT.EDU>,
"'bshannon@mit.edu'"
<bshannon@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'edie@mit.edu'" <edie@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 22 Jun 1999 11:34:39 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: barrett@mit.edu; cashaw@mit.edu; opsnote@mit.edu; esico@mit.edu;
> sfalconi@mit.edu; honiker@mit.edu; kelley@mit.edu; bshannon@mit.edu;
> shutdowns@mit.edu; edie@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Rescheduled Again - Bldg. E19 - 6th and 7th Floors Shutdown
> Request- Now for 6/28
>
>
Dear Everyone:
I have been advised there is a project going on in the Telecommunications
area on 6/25 after 5 PM. Therefore we have rescheduled the above shutdown
request to Monday, 6/28 from 3 PM - 11 PM.
Would you please let me know if this rescheduled date would be all right
with you or not.
Thank you again for your patience in this matter.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E19 - 6th and 7th Floors
> Date: 6/28/99
> Day: Monday
> Time: 3 PM - 11 PM
> System: Supply ventilation, supply cooling and supply heating
> Duration: 8 hours
> Reason:
> To service and repair fire damper.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating during
> shutdown period. (Heating is off this time of year anyway.)
>
>