[47787] in Hotline Meeting
Bldg. E19 - 6th and 7th Floors - 6/25 - Revised Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jun 22 09:56:38 1999
Message-Id: <ECFE33C8A3D4D111917900805FBE0000831928@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jwbarrett@mit.edu'" <jwbarrett@MIT.EDU>,
"'cashaw@mit.edu'"
<cashaw@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'esico@mit.edu'" <esico@MIT.EDU>,
"'sfalconi@mit.edu'"
<sfalconi@MIT.EDU>,
"'honiker@mit.edu'" <honiker@MIT.EDU>,
"'kelley@mit.edu'" <kelley@MIT.EDU>,
"'bshannon@mit.edu'"
<bshannon@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'edie@mit.edu'" <edie@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 22 Jun 1999 09:48:50 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: jwbarrett@mit.edu; cashaw@mit.edu; opsnote@mit.edu; esico@mit.edu;
> sfalconi@mit.edu; honiker@mit.edu; kelley@mit.edu; bshannon@mit.edu;
> shutdowns@mit.edu; edie@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E19 - 6th and 7th Floors - 6/25 - Revised Shutdown
> Request
>
>
Dear Everyone:
Would you please let me know if the new time for this shutdown request
better fits your schedules.
Thanks and I look forward to hearing from you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E19 - 6th and 7th Floors
> Date: 6/25/99
> Day: Friday
> Time: 3 PM - 11 PM
> System: supply ventilation, supply cooling and supply heating
> Duration: 8 hours
> Reason:
> To service and repair fire dampers.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating during
> shutdown period. (Heating is off this time of year anyway.)
>
>