Bldg. 2 - 2040 also entire building- 6/23 - Sprinkler Shutdown R

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 21 09:09:01 1999

Message-Id: <ECFE33C8A3D4D111917900805FBE0000831905@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'lnolan@mit.edu'" <lnolan@MIT.EDU>,
        "'cappucci@math.mit.edu'"
	 <cappucci@math.mit.edu>,
        "'duggin@math.mit.edu'" <duggin@math.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 21 Jun 1999 09:01:27 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	lnolan@mit.edu; cappucci@math.mit.edu; duggin@math.mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 2 - 2040  also entire building- 6/23 - Sprinkler
> Shutdown Request
> 
> 
The following sprinkler shutdown for Bldg 2 - 2040 as well as the entire
building on 6/23 is for your review and comment.  Would you please let me
know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 2 - 2040 (also entire buildng)
> Date: 6/23/99
> Day: Wednesday
> Time: 7:30 AM - 2:30 PM
> System: Fire Protection Water
> Duration: 7 hours
> Reason: 
> Tie in new sprinkler system to existing system.
> 
> Effect: 
> Loss of fire protection water to buildng 2 during the shutdown period.
> The Safety Office will be advised of this - that office will notify the
> Fire Department.
> 
> 