Bldgs. 2 - 6/16 - Critical Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 14 10:26:46 1999
Message-Id: <ECFE33C8A3D4D111917900805FBE0000831899@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'akelsey@mit.edu'" <akelsey@MIT.EDU>,
"'daisymae@math.mit.edu'"
<daisymae@math.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'capozzi@math.mit.edu'"
<capozzi@math.mit.edu>,
"'duggins@math.mit.edu'" <duggins@math.mit.edu>,
"'mbj@mit.edu'" <mbj@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 14 Jun 1999 10:19:28 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: akelsey@mit.edu; daisymae@math.mit.edu; shutdowns@mit.edu;
> schedule@mit.edu; capozzi@math.mit.edu; duggins@math.mit.edu; mbj@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 2 - 6/16 - Critical Shutdown Request
>
>
The following Critical shutdown request for Bldg. 2 on 6/16 is for your
review and comment. Would you please let me know whetehr this does or does
not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: 2
> Date: 6/16/99
> Day: Wednesday
> Time: 7 AM - 3 PM
> System: Compressed Control air and Compressed Lab air
> Duration: 8 hours
> Reason:
> Move pipes.
>
> Effect:
> Loss of compressed control air and compressed lab air in Building 2 during
> the shutdown period.
>
>