Bldg. 2 - 014, 001 to 013, 101 to 117, 201 to 221 and 301 to 325
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 11 08:55:21 1999
Message-Id: <ECFE33C8A3D4D111917900805FBE000083187D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mbj@mit.edu'" <mbj@MIT.EDU>, "'akelsey@mit.edu'" <akelsey@MIT.EDU>,
"'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
"'duggins@math.mit.edu'"
<duggins@math.mit.edu>,
"'schedule@mit.edu'" <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Date: Fri, 11 Jun 1999 08:48:01 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: mbj@mit.edu; akelsey@mit.edu; capozzi@math.mit.edu;
> duggins@math.mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu; shutdowns@mit.edu
> Subject: Bldg. 2 - 014, 001 to 013, 101 to 117, 201 to 221 and 301 to
> 325 - 6/15 - Shutdown Request
>
>
The following shutdown request for Bldg. 2 - 014, 001 to 013, 101 to 117,
201 to 221 and 301 to 325 on 6/15 is for your review and comment. Would
you please let me know whether this does or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 2 - 014, 001 to 013, 101 to 117, 201 to 221 and 301 to 325
> Date: 6/15/99
> Day: Tuesday
> Time: 7:30 AM - 3:30 PM
> System: Hot and cold domestic water; hot and cold lab process water
> Duration: 8 hours
> Reason:
> Tie-in for services to Building 2 new work.
>
> Effect:
> Building 2-001 to 013, 101 to 117, 201 to 221 and 301 to 325 will lose
> cold domestic water (bathrooms, eye washes and safety showers, kitchen
> faucets, drinking fountains); hot and cold lab processed water (water for
> lab equipment); and 2-111 will have all water with the exception of a
> safety shower.
>
>