[47709] in Hotline Meeting
Bldg. 10 - 050 - 6/7 - Emergency Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 7 14:25:21 1999
Message-Id: <ECFE33C8A3D4D111917900805FBE0000831833@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'otten@mit.edu'" <otten@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
"'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>,
Billy Homeyer
<whomeyer@PLANT.MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>
Date: Mon, 7 Jun 1999 14:18:00 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: otten@mit.edu; C-Zone; dcarlson@mit.edu; cappucci@mit.edu;
> jfreeman@mit.edu; mmahoney@mit.edu; Billy Homeyer; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldg. 10 - 050 - 6/7 - Emergency Shutdown
>
>
The following Emergency shutdown for Bldg. 10 - 050 on 6/7 is for your
information.
Andrea Nichols
Operations Center
8-7872
P.S. I am sending this information through at 2;25 PM on 6/7 (the clock on
my exchange mail is incorrect.)
AN
> Status: Emergency
> Building: 10-050
> Date: 6/7/99
> Day: Monday
> Time: 2:30 PM - 5:30 PM
> System: Supply Cooling (Air Handler system)
> Duration: 3 hours
> Reason:
> Strainer clogged - no cooling getting through to 10-050.
>
> Effect:
> Loss of supply cooling in 10-050.
>
>