Bldg. 2 and Bldg. 4 - 031 to 085, 131 to 185, 231 to 273 - 5/27 -

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon May 24 08:45:34 1999

Message-Id: <ECFE33C8A3D4D111917900805FBE00007B80D4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'fucillo@mit.edu'" <fucillo@MIT.EDU>, "'elp@mit.edu'" <elp@MIT.EDU>,
        "'jhlyons@mit.edu'" <jhlyons@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
        "'duggins@math.mit.edu'"
	 <duggins@math.mit.edu>,
        "'mbj@mit.edu'" <mbj@MIT.EDU>, "'akelsey@mit.edu'" <akelsey@MIT.EDU>,
        "'jhlyons@mit.edu'"
	 <jhlyons@MIT.EDU>,
        "'graham@mit.edu'" <graham@MIT.EDU>,
        "'ccarey@mit.edu'" <ccarey@MIT.EDU>, "'krf@mit.edu'" <krf@MIT.EDU>,
        "'jcentor@mit.edu'" <jcentor@MIT.EDU>, "'frc@mit.edu'" <frc@MIT.EDU>,
        "'griffin@mit.edu'" <griffin@MIT.EDU>,
        "'rrhonda@mit.edu'"
	 <rrhonda@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 24 May 1999 08:38:56 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	fucillo@mit.edu; elp@mit.edu; jhlyons@mit.edu; shutdowns@mit.edu;
> schedule@mit.edu; capozzi@math.mit.edu; duggins@math.mit.edu; mbj@mit.edu;
> akelsey@mit.edu; jhlyons@mit.edu; graham@mit.edu; ccarey@mit.edu;
> krf@mit.edu; jcentor@mit.edu; frc@mit.edu; griffin@mit.edu;
> rrhonda@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 2 and Bldg. 4 - 031 to 085, 131 to 185, 231 to 273 -
> 5/27 - Shutdown Request
> 
> 
The following shutdown request for Bldg. 2 and Bldg. 4 - 031 to 085, 131 to
185,  and  231 to 273 on 5/27 is for your information and comment.  Would
you please let me know whether this does or does not meet with your
approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Critical
> Building: 2 and 4 - 031 to 085, 131 to 185, 231 to 273
> Date: 5/27/99
> Day: Thursday
> Time: 12 AM - 7:30 AM
> System: Cold Domestic Water and cold Lab Process Water
> Duration: 7 1/2 hours
> Reason: 
> Water testing for lead.
> 
> Effect: 
> Los of cold domestic (no toilets, kitchen or bathroom faucets) and cold
> lab process (no lab process water to use with lab equipment)  in the above
> listed Building (2) and Bldg. 4 rooms only.
> 
> 