Bldgs. 33 and 35 - 5/12 PM - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed May 12 09:13:43 1999
Message-Id: <ECFE33C8A3D4D111917900805FBE00007B8053@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'dickp@mit.edu'"
<dickp@MIT.EDU>,
"'rdavies@mit.edu'" <rdavies@MIT.EDU>,
"'gallant@mit.edu'" <gallant@MIT.EDU>,
"'gerwent@mit.edu'"
<gerwent@MIT.EDU>,
"'kate@lids.mit.edu'" <kate@lids.mit.edu>,
"'stiffler@mit.edu'" <stiffler@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 12 May 1999 09:07:26 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: schedule@mit.edu; dickp@mit.edu; rdavies@mit.edu;
> gallant@mit.edu; gerwent@mit.edu; kate@lids.mit.edu; stiffler@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 33 and 35 - 5/12 PM - Shutdown Request
>
>
The following shutdown request for Bldgs. 33 and 35 for this evening
(5/12) is for your review and comment. We realize that this is very late
but wondered if this particular shutdown would be possible. Would you
please let me know whether this does or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 33 and 35
> Date: 5/12/99
> Day: Wednesday
> Time: 7 PM - 12 midnight
> System: Normal electrical Power
> Duration: 5 hours
> Reason:
> Demolition (interior) of building 33 for renovations.
>
> Effect:
> Loss of building power, computers, lighting, lighting
> corridors/stairs; supply cooling, compressed control and compressed
> lab air and sump pumps.
>
>