RE: Rescheduled - Bldg. 14 - All - 4/28 PM - 4/29 AM Shutdown Req

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Apr 22 14:39:50 1999

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'rdavies@mit.edu'"
	 <rdavies@MIT.EDU>, "'efc@mit.edu'" <efc@MIT.EDU>,
        "'kglavash@mit.edu'"
	 <kglavash@MIT.EDU>,
        "'nlowe@mit.edu'" <nlowe@MIT.EDU>,
        "'ellertsen@mit.edu'" <ellertsen@MIT.EDU>,
        "'mosh@mit.edu'"
	 <mosh@MIT.EDU>,
        "'susanne@mit.edu'" <susanne@MIT.EDU>,
        "'bkdavis@mitvma.mit.edu'" <bkdavis@mitvma.mit.edu>,
        "'clarices@mit.edu'"
	 <clarices@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Thu, 22 Apr 1999 14:34:16 -0400

Dear Everyone:
Because of an event that has been scheduled on 4/29 and 4/30 - the
shutdown request for Bldg. 14 - All Electrical has been rescheduled to
4/28 PM - 4/29 AM. Would you please let me know if these new dates meet
with your approval or do not.

Thank you again.

Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Normal
> > Building: 14 - All
> > Date: 4/28/29
> > Day: Wednesday PM - Thursday AM
> > Time: 10 PM (4/28) - 6 AM (4/29)
> > System: All Electric Power and lighting
> > Duration: 8 hours
> > Reason: 
> > To complete installation of high voltage switch.
> > 
> > Effect: 
> > Loss of building power, elevators, computers, lighting; Water:
> heating
> > hot water; air: supply ventilation, supply cooling, supply heating,
> > exhaust general air, exhaust toilet air and compressed control air;
> > Steam: condensate return.
>  
> 