Bldg. 14 - All - 4/29 PM - 4/30 AM Shutdown Request - Phase II

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Apr 20 12:30:05 1999

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'rdavies@mit.edu'"
	 <rdavies@MIT.EDU>, "'efc@mit.edu'" <efc@MIT.EDU>,
        "'kglavash@mit.edu'"
	 <kglavash@MIT.EDU>,
        "'nlowe@mit.edu'" <nlowe@MIT.EDU>,
        "'ellertsen@mit.edu'" <ellertsen@MIT.EDU>,
        "'mosh@mit.edu'"
	 <mosh@MIT.EDU>,
        "'susanne@mit.edu'" <susanne@MIT.EDU>,
        "'bkdavis@mitvma.mit.edu'" <bkdavis@mitvma.mit.edu>,
        "'clarices@mit.edu'"
	 <clarices@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 20 Apr 1999 12:24:18 -0400

> To: 	schedule@mit.edu; rdavies@mit.edu; efc@mit.edu;
> kglavash@mit.edu; nlowe@mit.edu; ellertsen@mit.edu; mosh@mit.edu;
> susanne@mit.edu; bkdavis@mitvma.mit.edu; clarices@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 14 - All - 4/29 PM - 4/30 AM Shutdown Request -
> Phase II
> 
> 
The following shutdown request for Bldg. 14 - All Electric Power and
Lighting - Phase II on 4/29 PM - 4/30 AM is for your information and
comment.  Would you please let me know whether this does or does not
meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 14 - All
> Date: 4/29/30
> Day: Thursday
> Time: 10 PM (4/29) - 6 AM (4/30)
> System: All Electric Power and lighting
> Duration: 8 hours
> Reason: 
> To compelte installation of high voltage switch.
> 
> Effect: 
> Loss of building power, elevators, computers, lighting; Water: heating
> hot water; air: supply ventilation, suppy cooling, supply heating,
> exhaust general air, exhaust toilet air and compressed control air;
> Steam: condensate return.
> 
> 