RE: Bldg. E38 - 5th Floor Core Area - 4/13 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Apr 9 10:54:15 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'tdownes@mit.edu'" <tdownes@MIT.EDU>,
"'davine@mit.edu'"
<davine@MIT.EDU>,
"'jensen@ilp.mit.edu'" <jensen@ilp.mit.edu>,
"'lhill@mit.edu'" <lhill@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'jeremias@mit.edu'" <jeremias@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Fri, 9 Apr 1999 10:47:53 -0400
Correction
I have just been informed that there will be no aid conditioning for
Bldg. E38 during the shutdown period.
Andrea Nichols
> ----------
> From: Andrea Nichols
> Sent: Friday, April 09, 1999 10:02 AM
> To: 'tdownes@mit.edu'; 'davine@mit.edu'; 'jeremias@mit.edu';
> 'jensen@ilp.mit.edu'; 'lhill@mit.edu'; 'shutdowns@mit.edu'
> Cc: Shutdown
> Subject: Bldg. E38 - 5th Floor Core Area - 4/13 Shutdown Request
> Importance: High
>
> The following shutdown request for Bldg. E38 - 5th Floor Core area on
> 4/13 is for your information and comment. Would you please let me know
> whether this does or does not have your approval.
>
> Thank you.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: E38 - 5th Floor Core Area
> > Date: 4/13/99
> > Day: Tuesday
> > Time: 7:30 AM - 2:30 PM
> > System: Chilled Water, Condenser Water
> > Duration: 7 hours
> > Reason:
> > Replacement of Chiller Unit #708161 with new unit (changing to
> Central
> > Chilled Water system).
> >
> > *Effect:
> > There will be no air conditioning in Bldg. E38 during this shutdown
> period.
> >
> >
>