RE: Bldgs. 33 Basement & 1st Floor and 35 - 4/5 - Shutdown Reque

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Apr 1 13:10:35 1999

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'dickp@mit.edu'"
	 <dickp@MIT.EDU>,
        "'rdavies@mit.edu'" <rdavies@MIT.EDU>,
        "'gerwent@mit.edu'" <gerwent@MIT.EDU>,
        "'stiffler@mit.edu'"
	 <stiffler@MIT.EDU>,
        "'kate@lids.mit.edu'" <kate@lids.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Thu, 1 Apr 1999 13:05:39 -0500

Update --this is to verify that this shutdown would affect any rooms in
the basement and 1st floor of Bldg. 33 and possibly all of Bldg. 35
(that is to be confirmed). The shutdown request at this point is simply
a heads up for potential work and a suggested date. Sorry for the
confusion.
Andrea Nichols

> ----------
> From: 	Andrea Nichols
> Sent: 	Thursday, April 01, 1999 10:47 AM
> To: 	'schedule@mit.edu'; 'dickp@mit.edu'; 'rdavies@mit.edu';
> 'gerwent@mit.edu'; 'stiffler@mit.edu'; 'kate@lids.mit.edu';
> 'shutdowns@mit.edu'
> Cc: 	Shutdown
> Subject: 	Bldgs. 33  Basement & 1st Floor and 35 - 4/5 - Shutdown
> Request
> Importance: 	High
> 
> > To: 	schedule@mit.edu; dickp@mit.edu; rdavies@mit.edu;
> > gerwent@mit.edu; stiffler@mit.edu; kate@lids.mit.edu;
> > shutdowns@mit.edu
> > Cc: 	shutdown@plant.mit.edu
> > Subject: 	Bldgs. 33  Basement & 1st Floor and 35 - 4/5 - Shutdown
> > Request
> > 
> > 
> The following shutdown request for Bldgs. 33 and 35 on 4/5 is for your
> information and comment. Would you please let me know whether this
> does
> or does not meet with your approval.
> 
> Thank you.
> 
> Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Normal
> > Building: 33 Basement & 1st Floor and 35
> > Date: 4/5/99
> > Day: Monday
> > Time: 7 AM - 3 PM
> > System: Chilled Water Pumps
> > Duration: 8 hours
> > Reason: 
> > Electrical demo in Bldg. 33 in the basement requires the pumps to be
> > disconnected and reconnected to a new transfomer.
> > 
> > Effect: 
> > Loss of chilled water (air conditioning) in Bldg. 33 - Basement and
> 1st floors and Bldg. 35
> > during shutdown period.
> > 
> > 
> 