RE: Bldg. E40 - 3/31 - Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Mar 29 08:47:48 1999

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'lhill@mit.edu'" <lhill@MIT.EDU>,
        "'michaela@mit.edu'"
	 <michaela@MIT.EDU>,
        "'pmosley@mit.edu'" <pmosley@MIT.EDU>,
        "'cfoglia@mit.edu'" <cfoglia@MIT.EDU>,
        "'achow@mit.edu'" <achow@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'jfob@mit.edu'"
	 <jfob@MIT.EDU>,
        "'sgraves@mit.edu'" <sgraves@MIT.EDU>, "'pal@mit.edu'"
	 <pal@MIT.EDU>,
        "'hanson@mit.edu'" <hanson@MIT.EDU>,
        "'sshurt@mit.edu'"
	 <sshurt@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Mon, 29 Mar 1999 08:43:03 -0500

Dear Everyone:
I goofed! - This shutdown is supposed to be for Wednesday, 3/31 (not
Tuesday as I had mentioned below). I apologize for the confusion -- it
is also supposed to be 60 degrees or higher on Wednesday, 3/31.

Andrea Nichols 
> ----------
> From: 	Andrea Nichols
> Sent: 	Monday, March 29, 1999 8:04 AM
> To: 	'lhill@mit.edu'; 'michaela@mit.edu'; 'pmosley@mit.edu';
> 'cfoglia@mit.edu'; 'achow@mit.edu'; 'shutdowns@mit.edu';
> 'jfob@mit.edu'; 'sgraves@mit.edu'; 'pal@mit.edu'; 'hanson@mit.edu';
> 'sshurt@mit.edu'
> Cc: 	Shutdown
> Subject: 	RE: Bldg. E40 - 3/31 - Shutdown Request
> Importance: 	High
> 
> Good morning everyone:
> The shutdown for Bldg. E40 is scheduled for Wednesday, 3/31. It is
> supposed to be 60 degrees outside so it shouldn't be too uncomfortable
> without air conditioning or heat. (There will be perimeter heat
> however.)
> 
> If anyone has any major objections, please let me know. Otherwise the
> work will go on.
> 
> Thank you.
> 
> Andrea Nichols
> 
> 	----------
> 	From: 	Andrea Nichols
> 	Sent: 	Thursday, February 25, 1999 10:16 AM
> 	To: 	'lhill@mit.edu'; 'michaela@mit.edu'; 'pmosley@mit.edu';
> 'cfoglia@mit.edu'; 'achow@mit.edu'; 'shutdowns@mit.edu';
> 'jfob@mit.edu'; 'sgraves@mit.edu'; 'pal@mit.edu'; 'hanson@mit.edu';
> 'sshurt@mit.edu'
> 	Cc: 	Shutdown
> 	Subject: 	Bldg. E40 - 3/31 - Shutdown Request
> 
> 	As a follow-up to the shutdown of 12/23 - the following shutdown
> request
> 	for Bldg. E40 - on 3/31 is for your review and comment. Would
> you please
> 	let me know whether this does or does not have your approval.
> 
> 	Thank you.
> 
> 	Andrea Nichols
> 	Operations Center
> 	8-7872
> 
> 	> Status: Normal
> 	> Building: E40
> 	> Date: 3/31/99
> 	> Day: Wednesday
> 	> Time: 8 AM - 4 PM
> 	> System: Supply ventilation, cooling and heating (Air Handler 1
> and
> 	> Return Fan 1)
> 	> Duration: 8 hours
> 	> Reason: 
> 	> Repairs to fans resulting from maintenance inspection of
> December,
> 	> 1998.
> 	> 
> 	> Effect: 
> 	> Loss of supply ventilation, cooling and heating although there
> will be
> 	> perimeter heat (radiators) during the shutdown period.
> 	> 
> 	> 
> 
> 