[47036] in Hotline Meeting
RE: Bldg. E40 - 3/31 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Mar 29 08:47:48 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'lhill@mit.edu'" <lhill@MIT.EDU>,
"'michaela@mit.edu'"
<michaela@MIT.EDU>,
"'pmosley@mit.edu'" <pmosley@MIT.EDU>,
"'cfoglia@mit.edu'" <cfoglia@MIT.EDU>,
"'achow@mit.edu'" <achow@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'jfob@mit.edu'"
<jfob@MIT.EDU>,
"'sgraves@mit.edu'" <sgraves@MIT.EDU>, "'pal@mit.edu'"
<pal@MIT.EDU>,
"'hanson@mit.edu'" <hanson@MIT.EDU>,
"'sshurt@mit.edu'"
<sshurt@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Mon, 29 Mar 1999 08:43:03 -0500
Dear Everyone:
I goofed! - This shutdown is supposed to be for Wednesday, 3/31 (not
Tuesday as I had mentioned below). I apologize for the confusion -- it
is also supposed to be 60 degrees or higher on Wednesday, 3/31.
Andrea Nichols
> ----------
> From: Andrea Nichols
> Sent: Monday, March 29, 1999 8:04 AM
> To: 'lhill@mit.edu'; 'michaela@mit.edu'; 'pmosley@mit.edu';
> 'cfoglia@mit.edu'; 'achow@mit.edu'; 'shutdowns@mit.edu';
> 'jfob@mit.edu'; 'sgraves@mit.edu'; 'pal@mit.edu'; 'hanson@mit.edu';
> 'sshurt@mit.edu'
> Cc: Shutdown
> Subject: RE: Bldg. E40 - 3/31 - Shutdown Request
> Importance: High
>
> Good morning everyone:
> The shutdown for Bldg. E40 is scheduled for Wednesday, 3/31. It is
> supposed to be 60 degrees outside so it shouldn't be too uncomfortable
> without air conditioning or heat. (There will be perimeter heat
> however.)
>
> If anyone has any major objections, please let me know. Otherwise the
> work will go on.
>
> Thank you.
>
> Andrea Nichols
>
> ----------
> From: Andrea Nichols
> Sent: Thursday, February 25, 1999 10:16 AM
> To: 'lhill@mit.edu'; 'michaela@mit.edu'; 'pmosley@mit.edu';
> 'cfoglia@mit.edu'; 'achow@mit.edu'; 'shutdowns@mit.edu';
> 'jfob@mit.edu'; 'sgraves@mit.edu'; 'pal@mit.edu'; 'hanson@mit.edu';
> 'sshurt@mit.edu'
> Cc: Shutdown
> Subject: Bldg. E40 - 3/31 - Shutdown Request
>
> As a follow-up to the shutdown of 12/23 - the following shutdown
> request
> for Bldg. E40 - on 3/31 is for your review and comment. Would
> you please
> let me know whether this does or does not have your approval.
>
> Thank you.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: E40
> > Date: 3/31/99
> > Day: Wednesday
> > Time: 8 AM - 4 PM
> > System: Supply ventilation, cooling and heating (Air Handler 1
> and
> > Return Fan 1)
> > Duration: 8 hours
> > Reason:
> > Repairs to fans resulting from maintenance inspection of
> December,
> > 1998.
> >
> > Effect:
> > Loss of supply ventilation, cooling and heating although there
> will be
> > perimeter heat (radiators) during the shutdown period.
> >
> >
>
>