[46997] in Hotline Meeting
Bldg. 14 - 4/1-2 - Normal Electrical Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Mar 23 08:48:13 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'in%\"sdl-adm-lib@mit.edu'"
<in@"sdl-adm-lib@mit.edu>, "'efc@mit.edu'" <efc@mit.edu>,
"'kglavash@mit.edu'" <kglavash@mit.edu>, "'nlow@mit.edu'" <nlow@mit.edu>,
"'ellertsen@mit.edu'" <ellertsen@mit.edu>, "'mosh@mit.edu'"
<mosh@mit.edu>, ">,
du'" <shutdowns@mit.edu>"@MIT.EDU
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 23 Mar 1999 08:43:40 -0500
> To: schedule@mit.edu; in%"sdl-adm-lib@mit.edu; efc@mit.edu;
> kglavash@mit.edu; nlow@mit.edu; ellertsen@mit.edu; mosh@mit.edu;
> susanne@mit.edu; bkdavis@mitvma.mit.edu; clarices@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 14 - 4/1-2 - Normal Electrical Power Shutdown
> Request
>
>
The following Normal Electrical Power shutdown request for Bldg. 14 on
4/1-2 is for your information and comment.
Would you please let me know whether this does or does not meet with
your approval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: Bldg. 14
> Date: 4/1/02
> Day: Thursday
> Time: 10 PM (4/1) - 6 AM (4/2)
> System: Normal Electrical Power
> Duration: 8 hours
> Reason:
> First of 2 shutdowns to replace high voltage G & W switch.
>
> Effect:
> Loss of Power: building power, elevators, computers, lighting; Water:
> heating hot water; air: supply ventilation, supply cooling, supply
> heating, exhaust general, exhaust toilet and compressed control air;
> Steam: condensate return;
>
>