[46966] in Hotline Meeting
Bldg. 4 - 034 - 4/5 - Asbestos Removal Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Mar 19 07:53:25 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.EDU>, Jack Narcotta <JNarcott@PLANT.MIT.EDU>,
"'tr6@mit.edu'" <tr6@MIT.EDU>, "'jdoucett@mit.edu'" <jdoucett@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>,
"'tdoyle@mit.edu'"
<tdoyle@MIT.EDU>,
"'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'" <cappucci@MIT.EDU>,
"'jfreeman@mit.edu'"
<jfreeman@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'ccarey@mit.edu'" <ccarey@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Date: Fri, 19 Mar 1999 07:48:57 -0500
> To: C-Zone; Jack Narcotta; tr6@mit.edu; jdoucett@mit.edu;
> mmahoney@mit.edu; tdoyle@mit.edu; dcarlson@mit.edu; cappucci@mit.edu;
> jfreeman@mit.edu
> Cc: shutdown@plant.mit.edu; ccarey@mit.edu; shutdowns@mit.edu
> Subject: Bldg. 4 - 034 - 4/5 - Asbestos Removal Notification
>
>
The following asbestos removal notification for Bldg. 4 - 034 on 4/5 is
for your information. If you have any question about this, please
contact Tammy Doyle at 3-5166.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 4 - 034
> Date: 4/5/99
> Day: Monday
> Time: 7 AM - 3 PM
> System: None - asbestos removal notification only
> Duration: 8 hours
> Reason:
> 10 linear feet of asbestos to be removed from water line insulation.
> There has been prior removal in this area.
>
> Effect:
> No access to 4-034 during asbestos removal period.
>
>