The following Critical shutdown request for Bldg. W20 has been
rescheduled to Thursday, 3/11. There will be large fans provided to
areas that will need them.
Would you please let me know if this new date would be all right with
you or not.
Thank you again for your time.
Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Critical
> > Building: W20
> > Date: 3/11/99
> > Day: Thursday
> > Time: 7 AM - 3 PM
> > System: Chilled Water (air conditioning)
> > Duration: 8 hours
> > Reason:
> > Installation of electrical disconnect switch on pump equipment.
> >
> > Effect:
> > Loss of chilled water (air conditioning) and supply cooling (air)
> > during shutdown period.
>
>