RE: Bldg. 2 - 2/25 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Feb 18 11:04:57 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'capozzi@math.mit.edu'"
<capozzi@math.mit.edu>,
"'duggins@math.mit.edu'" <duggins@math.mit.edu>,
"'mbj@mit.edu'" <mbj@MIT.EDU>,
"'daisymae@math.mit.edu'"
<daisymae@math.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Date: Thu, 18 Feb 1999 11:01:20 -0500
Update -
Dear Everyone:
I have updated this shutdown for your information. Yes, there will be
supply heating (from supply fans in the ceiling) that will be operating.
But the steam heat from radiators (known as perimeter heating) will be
shutdown.
I hope this answers your questions, concerns, etc. If not, please feel
free to contact me again.
Andrea Nichols
> The following shutdown request for Bldg. 2 on 2/25 is for your
> information. Would you please let me know whether this does or does
> not
> meet with your approval.
>
> Thank you.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 2
> > Date: 2/25/99
> > Day: Thursday
> > Time: 10 AM - 6 PM
> > System: Low Pressure Steam
> > Duration: 8 hours
> > Reason:
> > Replace riser valves.
> >
> > Effect:
> > Loss of steam heating (heat from radiators known as perimeter
> heating) in building. This will not affect supply heating (heat from
> supply fans in ceilings).
> >
> >
>