FW: Approved - Rescheduled - Bldg. 68 - All Emergency Power Syst

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Feb 3 11:41:30 1999

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-3rdShift <rm-3rdshift@MIT.EDU>,
        "'dcarlson@mit.edu'"
	 <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'" <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
        "'mmahoney@mit.edu'"
	 <mmahoney@MIT.EDU>, A-Zone <A-Zone@MIT.EDU>,
        Neil Tomlinson
	 <NTomlins@PLANT.MIT.EDU>,
        James Sullivan <jsulliva@PLANT.MIT.EDU>,
        Manuel Moreira <mmoreira@PLANT.MIT.EDU>,
        Paul Adams
	 <padams@PLANT.MIT.EDU>, Carl Hagge <CHagge@PLANT.MIT.EDU>,
        Joe Kay
	 <jakay@PLANT.MIT.EDU>,
        "'tomlynch@mit.edu'" <tomlynch@MIT.EDU>,
        Gerry Hughes <ghughes@PLANT.MIT.EDU>
Cc: "'jmganno@mit.edu'" <jmganno@MIT.EDU>,
        "'shutdown@plant.mit.edu'"
	 <shutdown@plant.mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'fucillo@mit.edu'"
	 <fucillo@MIT.EDU>
Date: Wed, 3 Feb 1999 11:38:12 -0500

The following approved rescheduled All Emergency Power System for Bldg.
68 now to be held on 3/5 is for your information.

Andrea Nichols
> 	Operations Center
> 	8-7872
> 
> 	> Status: Normal
> 	> Building: 68 - Entire Building Including Animal Quarters
> 	> Date: 3/05/98
> 	> Day: Friday
> 	> Time: 12:01 AM - 6:30 AM
> 	> System: Emergency Power (emergency lighting, elevators, animal
> care area, HVAC equipment, exhaust fans, outlets in labs.
> 	> Duration: 6 1/2 hours (outages - one at around 12:01 AM and
> the other at around 6:00 AM)
> 	> Reason: 
> 	> To test emergency generator - which will be momentary during
> the 6 1/2-hour shutdown.
> 	> 
> 	> Effect: 
> 	> The effect will be a momentary loss of emergency power as the
> 	> automatic transfer switch (ATS) transfers from Normal power to
> 	> Emergency power at the beginning of the test.
> 	> There will be another identical momentary shutdown at the end
> of the
> 	> test as the ATS transfers back to Normal power.
> 	> The effects to the Animal care Facility in the sub-basement
> will be
> 	> more lengthy as HVAC equipment cycles through programs that
> keep it
> 	> off longer.
> 	> There are many labs throughout the building with emergency
> outlets
> > that will have the momentary outages described above. 
> 
>        Facilities will provide adequate manpower to monitor alarms and
> respond to any problems that may arise.
> 