RE: Rescheduled Again - Bldg. 9 - Now for 2/9 All electric Power
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jan 28 09:45:21 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: jobrien@MIT.EDU, mshiffer@MIT.EDU, pguyer@MIT.EDU, shutdowns@MIT.EDU,
mitvideo@MIT.EDU, "'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'westlund@mit.edu'" <westlund@MIT.EDU>, "'krp@mit.edu'" <krp@MIT.EDU>
Date: Thu, 28 Jan 1999 09:42:18 -0500
Dear Everyone:
We are trying once again to meet everyone's requests with this shutdown.
Would you please let me know if Tuesday, February 9 from 6AM - 6:30 AM
would best fit your schedule. Some of you want this in the very early
morning (3 AM or so) --which doesn't bode well with others --some want
this in the evening -- which doesn't fit in with other department
schedules - and all of you certainly don't want this in the daytime.
I would appreciate your letting me know about this time new at your
convenience.
Thank you again and again.
Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 9
> > Date: 2/9/99
> > Day: Tuesday
> > Time: 6 AM - 6:30 AM
> > System: All Electric power & Lighting
> > Duration: 30 minutes
> > Reason:
> > To replace faulty fuses that were found during last shutdown.
> >
> > Effect:
> > Loss of Power: Access controls, building power, elevators,
> computers,
> > telephones, lighting; Water: chilled water (air
> conditioning); and
> > heating hot water; Air: supply ventilation, supply cooling,
> supply
> > heating, exhaust general and exhaust toilet air;
>
>