[46444] in Hotline Meeting
RE: Bldgs. E17, E18 and E19 - 1/29 - 480 Volt Electrical Shutdo
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jan 28 07:10:00 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jmedeiro@mit.edu'" <jmedeiro@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'cjbeal@mit.edu'" <cjbeal@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Thu, 28 Jan 1999 07:07:00 -0500
Reminder -- Would you please let me know by noon time today if the above
shutdown meets with your approval or not.
Thank you.
Andrea Nichols
> ----------
> From: Andrea Nichols
> Sent: Wednesday, January 20, 1999 2:56 PM
> To: 'wardd@mit.edu'; 'jmganno@mit.edu'; 'shyoung@mit.edu';
> 'aufiero@mit.edu'; 'rmelo@mit.edu'; 'jmedeiro@mit.edu'; Plant-All;
> 'opsnote@mit.edu'; 'shutdowns@mit.edu'; 'cjbeal@mit.edu';
> 'amba@mit.edu'
> Cc: Shutdown
> Subject: Bldgs. E17, E18 and E19 - 1/29 - 480 Volt Electrical
> Shutdown Request
> Importance: High
>
> > Subject: Bldgs. E17, E18 and E19 - 1/29 - 480 Volt Electrical
> > Shutdown Request
> >
> >
> The following shutdown request for Bldgs. E17, E18 and E19 on 1/29 is
> for your review and comment. Would you please let me know whether this
> does or does not have your approval.
>
> This is the third and final phase of this project.
>
> Thank you and I look forward to hearing from you.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Critical
> > Building: E17, E18 and E19
> > Date: 1/29/99
> > Day: Friday
> > Time: 6 AM - 6:30 AM
> > System: 480 Volt Electrical
> > Duration: 1/2 hour
> > Reason:
> > Install permanet main breaker in 480 volt main switchgear.
> >
> > Effect:
> > Power: Loss of Freight Elevator in E17 and E18; Water: loss of
> > chilled water (air conditioning) in E17 and E18 Animal Quarters as
> > well as remainder of E17, E18 and E19, E17-347B, 350, 350A and 360,
> > loss of heating hot water in E17 and 18; air: supply ventilation,
> > supply cooling, supply heating, exhaust-laboratory, exhaust-general,
> > exhaust-toilet, compressed control, compressed lab and lab vacuum
> air.
> > Note there will be an emergency generator running to supply power to
> > the Animal Quarters in E17 and E18. It is imperative that this work
> > be complete by 6:30 AM as cage washers will be reporting to work at
> > that time.
>
>