From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: jobrien@MIT.EDU, mshiffer@MIT.EDU, pguyer@MIT.EDU, shutdowns@MIT.EDU,
mitvideo@MIT.EDU, "'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'westlund@mit.edu'" <westlund@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Mon, 25 Jan 1999 14:52:59 -0500
Dear Everyone:
It has been requested that this half hour shutdown take place in the
evening rather than early morning. Would you please let me know if
Thursday, February 4 from 9 - 9:30 PM would fit in with your schedule.
Please advise and thanks.
Andrea Nichols
Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 9
> > Date: 2/4/99
> > Day: Thursday
> > Time: 9 PM - 9:30 PM
> > System: All Electric power & Lighting
> > Duration: 30 minutes
> > Reason:
> > To replace faulty fuses that were found during last shutdown.
> >
> > Effect:
> > Loss of Power: Access controls, building power, elevators,
> computers,
> > telephones, lighting; Water: chilled water (air conditioning); and
> > heating hot water; Air: supply ventilation, supply cooling, supply
> > heating, exhaust general and exhaust toilet air;
>