[46272] in Hotline Meeting
Bldgs. 2, 6, 6A & 14 1/12 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jan 6 10:16:04 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'duggins@math.mit.edu'"
<duggins@math.mit.edu>,
"'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
"'mbj@mit.edu'" <mbj@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'adams@mitlns.mit.edu'" <adams@mitlns.mit.edu>,
"'ccarey@mit.edu'"
<ccarey@MIT.EDU>,
"'naylor@mit.edu'" <naylor@MIT.EDU>, "'elp@mit.edu'"
<elp@MIT.EDU>,
"'farideh@mit.edu'" <farideh@MIT.EDU>,
"'rdavies@mit.edu'" <rdavies@MIT.EDU>,
"'sbritt@mit.edu'"
<sbritt@MIT.EDU>,
"'ericf@mit.edu'" <ericf@MIT.EDU>,
"'kglavash@mit.edu'" <kglavash@MIT.EDU>,
"'nlowe@mit.edu'"
<nlowe@MIT.EDU>,
"'narnia@mit.edu'" <narnia@MIT.EDU>, "'mosh@mit.edu'"
<mosh@MIT.EDU>,
"'susanne@mit.edu'" <susanne@MIT.EDU>,
"'bkdavis@mitvma.mit.edu'" <bkdavis@mitvma.mit.edu>,
"'jhlyons@mit.edu'"
<jhlyons@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
Joe Collins
<JCollins@PLANT.MIT.EDU>
Date: Wed, 6 Jan 1999 10:13:32 -0500
> To: schedule@mit.edu; duggins@math.mit.edu; capozzi@math.mit.edu;
> mbj@mit.edu; shutdowns@mit.edu; adams@mitlns.mit.edu; ccarey@mit.edu;
> naylor@mit.edu; elp@mit.edu; farideh@mit.edu; rdavies@mit.edu;
> sbritt@mit.edu; ericf@mit.edu; kglavash@mit.edu; nlowe@mit.edu;
> narnia@mit.edu; mosh@mit.edu; susanne@mit.edu; bkdavis@mitvma.mit.edu;
> jhlyons@mit.edu
> Cc: shutdown@plant.mit.edu; Joe Collins
> Subject: Bldgs. 2, 6, 6A & 14 1/12 Shutdown Request
>
>
The following shutdown request for Bldgs. 2, 6, 6A and 14 on 1/12 is for
your information and comment. Would you please let me know whether this
does or does not have your approval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 2, 6, 6A and 14
> Date: 1/12/99
> Day: Tuesday
> Time: 7:30 AM - 3:30 PM
> System: All water - hot and cold domestic and hot and cold lab process
> Duration: 8 hours
> Reason:
> Tie in new backflow preventers and add new valves.
>
> Effect:
> Loss of all water in Bdlgs. 2, 6, 6A and 14 with the exception od
> e-ionized water. This means that no bathrooms, kitchen faucets,
> drinking fountains or equipment requiring hot and cold lab process
> water will be operational during the shutdown period.
>
>