[46091] in Hotline Meeting
RE: Rescheduled --Bldg. 3 - 4th Floor Supply Cooling Shutdown Req
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Dec 7 08:13:43 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'pmccosco@mit.edu'"
<pmccosco@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'jobrien@mit.edu'" <jobrien@MIT.EDU>,
"'altonero@mit.edu'"
<altonero@MIT.EDU>,
"'ndk@mit.edu'" <ndk@MIT.EDU>, "'decarli@mit.edu'"
<decarli@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, "'anton@mit.edu'" <anton@MIT.EDU>,
C-Zone <C-Zone@MIT.EDU>
Date: Mon, 7 Dec 1998 08:12:06 -0500
Dear Everyone:
The new requested rescheduled dates for the above shutdown are 12/21/98
through 1/20/99. Would you please let me know if these new dates better
fits in with your schedules.
Thanks very much.
Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 3 - 4fh floor
> > Date: 12/21/98 - 1/20/99
> > Day: Monday (12/21/98) - Wednesday (1/20/99)
> > Time: 7:30 AM (12/21) - 3:30 PM (1/20)
> > System: Supply Cooling - PM#716892 (Air Handler 6 - Fan
> Supply)
> > Duration: 20 days
> > Reason:
> > Replacing Supply Cooling Ventilation Unit (PM#716892 (Air
> Handler 6-fan supply)
>
> > Effect:
> > Loss of supply cooling and smoke detector in PM#716892 during
> 20 day shutdown period.
>
>
>